9242 N HAYVENHURST AVE 91343
Certificate Information: 9242 N HAYVENHURST AVE 91343
- Application / Permit
- 23016-20000-06870
- Plan Check / Job No.
- B23VN02958
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/7/2023
- Issuing Office
- Current Status
- CofO Issued on 11/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2023 | OMAR GARNICA |
| Corrections Issued | 3/15/2023 | OMAR GARNICA |
| Plan Check Approved | 4/2/2023 | SARKIS HARABEDIAN |
| Issued | 4/7/2023 | APPLICANT |
| CofO in Progress | 10/10/2023 | RAUL OLAGI |
| CofO Issued | 11/28/2023 | RUBEN SALAS |
| Permit Finaled | 11/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 3/21/2023 | SPENCER WEJROWSKI |
| Address approval | Cleared | 3/29/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/29/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/7/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/7/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/7/2023 | Partial Approval | RAUL OLAGI |
| Sewer | 6/7/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 6/7/2023 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 6/22/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/27/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 6/27/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 6/27/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 6/27/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 7/5/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 7/5/2023 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 7/5/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 7/13/2023 | Approved | RAUL OLAGI |
| Insulation | 7/13/2023 | Approved | RAUL OLAGI |
| Shower Pan | 7/13/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 7/24/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/24/2023 | Approved | RAUL OLAGI |
| Final | 9/14/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/14/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 9/14/2023 | Corrections Issued | RAUL OLAGI |
| Final | 9/29/2023 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 9/29/2023 | Approved | RAUL OLAGI |
| Final | 10/10/2023 | OK to Issue CofO | RAUL OLAGI |