6316 N BELLAIRE AVE 91606

Certificate Information: 6316 N BELLAIRE AVE 91606

Application / Permit
23016-20000-06863
Plan Check / Job No.
B23VN02948
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Conversion and addition to existing detached garage with attached storage at the rear of the lot to ADU per LAMC 12.22 A.33 (c)-(d). All work done per engineered design. ***SEE COMMENTS***
Permit Issued
Issued on 8/29/2023
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2023 APPLICANT
Assigned to Plan Check Engineer 3/15/2023 DANIEL SMILEY
Corrections Issued 3/16/2023 DANIEL SMILEY
Applicant returned to address corrections 5/17/2023 VICTOR CHEN
Applicant returned to address corrections 7/20/2023 VICTOR CHEN
Applicant returned to address corrections 8/22/2023 VICTOR CHEN
Plan Check Approved 8/29/2023 LUKE GONZALES
Issued 8/29/2023 APPLICANT
CofO in Progress 5/6/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 5/29/2024 RUBEN SALAS
CofO Issued 5/29/2024 RUBEN SALAS
Permit Finaled 5/29/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/2/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/3/2023 NIKKI ZULUETA
Sewer availability Cleared 5/3/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 5/12/2023 NIKKI ZULUETA
Construction near power lines Cleared 6/5/2023 TINA MIRANDA
Construction within easement Cleared 6/5/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/8/2023 Approved KIRK SANDERS
Underground Mechanical 11/8/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Corrections Issued KIRK SANDERS
Green Building Rough 11/27/2023 Not Ready for Inspection KIRK SANDERS
Deputy Wood Construction 11/30/2023 Conditional Approval JUAN VALENZUELA
HVAC-Rough 12/6/2023 Corrections Issued JOSE AVILA
HVAC-Rough 12/8/2023 Approved JOSE AVILA
PLUMBING-Rough 12/8/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 12/18/2023 Conditional Approval JOSE AVILA
Green Building Rough 12/18/2023 Approved JOSE AVILA
Insulation 12/26/2023 Approved JOSE AVILA
Interior/Exterior Lathing 12/26/2023 Approved JOSE AVILA
Drywall Nailing 1/3/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 1/3/2024 Approved KIRK SANDERS
Shower Pan 1/3/2024 Approved KIRK SANDERS
Gas Test 3/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 3/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 3/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 3/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Sewer 3/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 3/20/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/16/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/18/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 4/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/18/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 4/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 4/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 4/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Final 5/3/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 5/3/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ