736 1/4 E 74TH ST 90001
Certificate Information: 736 1/4 E 74TH ST 90001
- Application / Permit
- 23016-20000-06748
- Plan Check / Job No.
- B23VN02883
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE (355SQFT) AND RECROOM (312 S.F ) TO (N) ATTACHED ACCESSORY DWLLEING UNIT (667SQFT) PER LAMC 12.22 A.33(c) AND (e) .
- Permit Issued
- Issued on 9/4/2023
- Issuing Office
- Current Status
- CofO Issued on 10/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/14/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/15/2023 | WEIJIAN HUANG |
| Plan Check Approved | 9/1/2023 | KHUONG TRUONG |
| Issued | 9/4/2023 | APPLICANT |
| CofO in Progress | 10/21/2024 | MICHAEL LEWIS |
| No Progress | 10/21/2024 | MICHAEL LEWIS |
| CofO in Progress | 10/21/2024 | MICHAEL LEWIS |
| Permit Finaled | 10/24/2024 | RUBEN SALAS |
| CofO Issued | 10/24/2024 | RUBEN SALAS |
| Permit Finaled | 10/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/24/2023 | JEANIE LAM |
| Address approval | Cleared | 4/25/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2023 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 5/9/2023 | ISMAEL HERNANDEZ |
| Historic monument | Cleared | 6/7/2023 | MAX LODER |
| Community Plan Implem. Overlay | Cleared | 6/9/2023 | HELEN JADALI |
| Construction within easement | Cleared | 8/29/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/16/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 10/19/2023 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 10/25/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 11/6/2023 | No Access for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | No Access for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 11/6/2023 | No Access for Inspection | MICHAEL LEWIS |
| Gas Test | 12/20/2023 | No Access for Inspection | MICHAEL LEWIS |
| Underground Mechanical | 12/26/2023 | Corrections Issued | DAVID FEILER |
| Wood Frame | 12/26/2023 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | No Access for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/8/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Green Building Rough | 3/8/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| HVAC-Rough | 3/8/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/14/2024 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/14/2024 | No Access for Inspection | MICHAEL LEWIS |
| Green Building Rough | 5/14/2024 | No Access for Inspection | MICHAEL LEWIS |
| HVAC-Rough | 5/14/2024 | No Access for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 5/14/2024 | No Access for Inspection | MICHAEL LEWIS |
| Underground Mechanical | 5/23/2024 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 5/30/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/5/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 6/5/2024 | Corrections Issued | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 6/6/2024 | Conditional Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/7/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 6/7/2024 | Corrections Issued | MICHAEL LEWIS |
| Wood Frame | 6/7/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/13/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 6/13/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 6/21/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 6/21/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/1/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Approved | MICHAEL LEWIS |
| Insulation | 7/1/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/2/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/3/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/9/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/9/2024 | Approved | MICHAEL LEWIS |
| Insulation | 7/9/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/9/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/12/2024 | Corrections Issued | MICHAEL LEWIS |
| Drywall Nailing | 7/16/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 7/26/2024 | Approved | ALEX COLIN |
| Final | 8/28/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 8/28/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 8/28/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/11/2024 | Approved | MICHAEL LEWIS |
| Final | 9/17/2024 | Partial Inspection | MICHAEL LEWIS |
| Service/Power Release | 9/17/2024 | Partial Inspection | MICHAEL LEWIS |
| Final | 10/18/2024 | OK to Issue CofO | MICHAEL LEWIS |