6534-6536 N VALLEY CIRCLE BLVD 91307

Certificate Information: 6534-6536 N VALLEY CIRCLE BLVD 91307

Application / Permit
23016-20000-06604
Plan Check / Job No.
B23VN02825
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Garage Conversion to JADU per GCS65852.2(e)(1)(A) and 65852.22 and WFPP in an (E) 1-Story SFD
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2023 APPLICANT
Assigned to Plan Check Engineer 3/10/2023 DAVID CASTILLO
Corrections Issued 3/11/2023 DAVID CASTILLO
Plan Check Approved 4/17/2023 ARSALAN SHABESTARI
Issued 4/17/2023 APPLICANT
CofO in Progress 8/30/2023 TROY SANDERS
Permit Finaled 9/11/2023 JOHN JANSON
CofO Issued 9/11/2023 JOHN JANSON
Permit Finaled 9/11/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/1/2023 ROMAN GUTIERREZ
Sewer availability Cleared 4/1/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/4/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2023 Approved TROY SANDERS
Deputy Reinf. Concrete 5/8/2023 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 5/9/2023 Approved TROY SANDERS
PLUMBING-Rough 5/9/2023 Partial Approval TROY SANDERS
Sewer 5/9/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 5/31/2023 Partial Approval TROY SANDERS
ELECTRICAL-Rough 5/31/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Order to Comply Issued TROY SANDERS
HVAC-Rough 5/31/2023 Approved TROY SANDERS
PLUMBING-Rough 5/31/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Approved HORACE FULTZ
Insulation 6/6/2023 Approved HORACE FULTZ
Interior/Exterior Lathing 6/6/2023 Partial Approval HORACE FULTZ
Drywall Nailing 6/13/2023 Approved HORACE FULTZ
Interior/Exterior Lathing 6/13/2023 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 8/18/2023 Approved TROY SANDERS
ELECTRICAL-Final 8/18/2023 Approved TROY SANDERS
Final 8/18/2023 Corrections Issued TROY SANDERS
HVAC-Final 8/18/2023 Approved TROY SANDERS
PLUMBING-Final 8/18/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 8/18/2023 Approved TROY SANDERS
Final 8/29/2023 OK to Issue CofO TROY SANDERS