14603 W RUNNYMEDE ST 91405

Certificate Information: 14603 W RUNNYMEDE ST 91405

Application / Permit
23016-20000-06594
Plan Check / Job No.
B23VN02817
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) attached garage to ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
Issued on 4/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/15/2023 APPLICANT
Assigned to Plan Check Engineer 3/21/2023 SHANGQIN XIE
Corrections Issued 3/22/2023 SHANGQIN XIE
Plan Check Approved 4/6/2023 FARSHAD ALIMOHAMADI
Issued 4/17/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/29/2023 FERNANDO GIL
Miscellaneous Cleared 3/29/2023 FERNANDO GIL
Sewer availability Cleared 3/29/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 3/31/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 6/24/2025 Approved VINCENT HANLEY
PLUMBING-Rough 6/24/2025 Partial Approval VINCENT HANLEY
Sewer 6/24/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/7/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Approved JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 8/7/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/13/2025 Conditional Approval JOSE AVILA
HVAC-Rough 8/13/2025 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 8/13/2025 Approved JOSE AVILA
HVAC-Rough 8/27/2025 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 9/4/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 9/4/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved VINCENT HANLEY
HVAC-Rough 9/4/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 9/30/2025 Approved VINCENT HANLEY
Green Building Rough 9/30/2025 Approved VINCENT HANLEY
HVAC-Rough 9/30/2025 Approved VINCENT HANLEY
Insulation 10/23/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/23/2025 Partial Approval VINCENT HANLEY
Drywall Nailing 11/21/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/21/2025 Approved JOSE AVILA