6227 N SHIRLEY AVE 91335
Certificate Information: 6227 N SHIRLEY AVE 91335
- Application / Permit
- 23016-20000-06144
- Plan Check / Job No.
- B23VN02658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 3/11/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/13/2023 | APPLICANT |
| Plan Check Approved | 6/27/2023 | SERGIO MUNIZ |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 4/8/2024 | ALEXANDER HANDY |
| Permit Finaled | 5/6/2024 | JOHN JANSON |
| CofO Issued | 5/6/2024 | JOHN JANSON |
| Permit Finaled | 5/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/14/2023 | DAGOVERTO GUERRERO |
| ZI | Cleared | 3/15/2023 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 6/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/30/2023 | Not Ready for Inspection | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 6/30/2023 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 6/30/2023 | Not Ready for Inspection | HORACE FULTZ |
| Gas Test | 6/30/2023 | Not Ready for Inspection | HORACE FULTZ |
| HVAC-Rough | 6/30/2023 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 6/30/2023 | Corrections Issued | HORACE FULTZ |
| Pre-Inspection | 6/30/2023 | Not Ready for Inspection | HORACE FULTZ |
| Sewer | 6/30/2023 | Not Ready for Inspection | HORACE FULTZ |
| Wood Frame | 6/30/2023 | Not Ready for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 7/24/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 7/24/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 7/24/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/24/2023 | Approved | ALEXANDER HANDY |
| Gas Test | 7/24/2023 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 7/24/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 7/24/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 7/24/2023 | Partial Approval | ALEXANDER HANDY |
| Pre-Inspection | 7/24/2023 | Approved | ALEXANDER HANDY |
| Sewer | 7/24/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 7/24/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/17/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 8/17/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 8/17/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 8/17/2023 | Approved | ALEXANDER HANDY |
| Insulation | 8/18/2023 | Approved | ALEXANDER HANDY |
| Shower Pan | 8/18/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 8/23/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 8/23/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/6/2023 | Approved | ALEXANDER HANDY |
| Final | 11/6/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 11/6/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 11/6/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 11/6/2023 | Approved | ALEXANDER HANDY |
| Final | 4/3/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 4/3/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/5/2024 | Approved | ALEXANDER HANDY |
| Final | 4/5/2024 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 4/5/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/5/2024 | Approved | ALEXANDER HANDY |