1050 W CHILDS WAY 90089
Certificate Information: 1050 W CHILDS WAY 90089
- Application / Permit
- 23016-20000-06117
- Plan Check / Job No.
- B23VN02645
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePLAN- OFFICE T.I. 4TH FLOOR OFFICES 400, 401, 405 AND 410 NON-STRUCTURAL INTERIOR RENOVATIONS, INCLUDING NEW PARTITIONS AND FINISHES
- Permit Issued
- Issued on 7/24/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/27/2024
Permit Application Status History
| Submitted | 3/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2023 | DANIEL YIP |
| Corrections Issued | 3/7/2023 | DANIEL YIP |
| Plan Check Approved | 3/14/2023 | DANIEL YIP |
| Issued | 7/24/2023 | APPLICANT |
| Permit Finaled | 8/26/2024 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/10/2023 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 3/10/2023 | GRACIELA ACOSTA |
| Specific Plan | Cleared | 3/10/2023 | RAFAEL FONTES |
Contact Information
| Contractor | Global Building Corporation; Lic. No.: 969892-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/1/2023 | Approved | ALAN MORELOS |
| Insulation | 8/2/2023 | Approved | ALAN MORELOS |
| Drywall Nailing | 8/8/2023 | Approved | ALAN MORELOS |
| T-Bar Ceiling | 9/14/2023 | Not Ready for Inspection | ALAN MORELOS |
| T-Bar Ceiling | 9/15/2023 | Approved | ALAN MORELOS |
| Final | 10/16/2023 | Partial Approval | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV No Gas | MARTIN TAVITIAN |
| Smoke Detectors | 10/16/2023 | Approved | MARTIN TAVITIAN |
| T-Bar Ceiling | 7/29/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| T-Bar Ceiling | 8/13/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 8/26/2024 | Permit Finaled | ALFREDO LOPEZ |