6613 N ZELZAH AVE 91335

Certificate Information: 6613 N ZELZAH AVE 91335

Application / Permit
23016-20000-05967
Plan Check / Job No.
B23VN02566
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19'-8" x 5'-6" ADDITION AND INTERIOR REMODEL OF (E) KITCHEN AND BATHROOM TO (E) SFD.
Permit Issued
Issued on 3/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/1/2023 MOHAMMAD ESMAILI
Issued 3/9/2023 APPLICANT
CofO in Progress 1/17/2024 JEFFREY BULL
Permit Finaled 1/18/2024 JOHN JANSON
CofO Issued 1/18/2024 JOHN JANSON
Permit Finaled 1/18/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/2/2023 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/3/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 3/3/2023 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 3/3/2023 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 3/3/2023 JOSE DUARTE-DIAZ

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor S K Home Designs And Remodeling; Lic. No.: 1026362-B PO BOX 16700      ENCINO, CA 91416

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/30/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 8/31/2023 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 9/21/2023 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Approved JEFFREY BULL
Green Building Rough 9/21/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 9/21/2023 Not Ready for Inspection JEFFREY BULL
Special/Order Compliance 9/21/2023 Corrections Issued JEFFREY BULL
Deputy Wood Construction 9/22/2023 Conditional Approval DAVID SCANTLIN
BUILDING-Rough-Frame 9/27/2023 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 9/27/2023 Approved JEFFREY BULL
Final 9/27/2023 Not Ready for Inspection JEFFREY BULL
Footing/Foundation/Slab 9/27/2023 Approved JEFFREY BULL
Green Building Final 9/27/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 9/27/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 9/27/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 9/27/2023 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 10/2/2023 Partial Approval JEFFREY BULL
Shower Pan 10/2/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/4/2023 Approved JEFFREY BULL
Drywall Nailing 10/19/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 1/2/2024 Approved JEFFREY BULL
Final 1/2/2024 Corrections Issued JEFFREY BULL
Green Building Final 1/2/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 1/2/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 1/2/2024 Not Ready for Inspection JEFFREY BULL
Final 1/11/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 1/11/2024 Approved JEFFREY BULL
Smoke Detectors 1/11/2024 Approved JEFFREY BULL