6937-6939 N SIMPSON AVE 91605
Certificate Information: 6937-6939 N SIMPSON AVE 91605
- Application / Permit
- 23016-20000-05963
- Plan Check / Job No.
- B23VN02561
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: CONVERT (E) ATT GARAGE, STORAGE ROOM AND (E) RECROOM/DEN AND BATHROOM WITHIN (E) DUPLEX INTO (N) 686 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) (FRONT BUILDING). ADDRESS RANGE INCLUDES 6937 1/2 SIMPSON AVE FOR ADU.
- Permit Issued
- Issued on 2/6/2024
- Issuing Office
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/6/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/11/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 1/31/2024 | OMAR GARNICA |
| Issued | 2/6/2024 | APPLICANT |
| CofO in Progress | 8/12/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
| CofO Issued | 8/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/16/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Inhance Construction Inc; Lic. No.: 1073871-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/6/2024 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 3/26/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 4/5/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/5/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/9/2024 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 4/9/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 4/29/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 4/29/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 4/29/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/30/2024 | Corrections Issued | JOHN HAYES |
| Deputy Wood Construction | 4/30/2024 | Partial Approval | JOHN HAYES |
| Green Building Rough | 4/30/2024 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 4/30/2024 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 5/8/2024 | Corrections Issued | JOHN HAYES |
| Deputy Wood Construction | 5/8/2024 | Conditional Approval | ROBERT GOLD |
| Green Building Rough | 5/8/2024 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 5/8/2024 | Partial Approval | JOHN HAYES |
| Shower Pan | 5/8/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/10/2024 | Approved | JOHN HAYES |
| Wood Frame | 5/10/2024 | Approved | JOHN HAYES |
| Insulation | 5/13/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 5/21/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/31/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 8/12/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |