20314-20316 W MOBILE ST 91306

Certificate Information: 20314-20316 W MOBILE ST 91306

Application / Permit
23016-20000-05902
Plan Check / Job No.
B23VN02541
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage into ADU per CA Govt. Code 65852.2(e)(1)(A). All work per arch **ePLAN**
Permit Issued
Issued on 4/16/2025
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 VICTOR CHEN
Corrections Issued 3/7/2023 VICTOR CHEN
Plan Check Approved 4/6/2023 WEIJIAN HUANG
Issued 4/16/2025 APPLICANT
CofO in Progress 12/12/2025 GEVORK IPCHYAN
Permit Finaled 2/26/2026 JOHN JANSON
CofO Issued 2/26/2026 JOHN JANSON
Permit Finaled 2/26/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/9/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/9/2023 LEE GUILBEAUX
Sewer availability Cleared 3/9/2023 LEE GUILBEAUX

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2025 Partial Inspection HENRY KIM
Deputy Drilled-In Anchors 8/22/2025 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 8/26/2025 Not Ready for Inspection ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 8/26/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 8/26/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 8/26/2025 Not Ready for Inspection ALEXANDER HANDY
Sewer 8/26/2025 Not Ready for Inspection ALEXANDER HANDY
Underground Mechanical 8/26/2025 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 9/3/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 9/3/2025 Partial Approval ALEXANDER HANDY
Sewer 9/3/2025 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 9/25/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 10/2/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 10/2/2025 Approved ALEXANDER HANDY
Sewer 10/2/2025 Approved ALEXANDER HANDY
Underground Mechanical 10/2/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 10/8/2025 Conditional Approval ALEXANDER HANDY
Wood Frame 10/8/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 10/16/2025 Partial Approval ROBERT GOLD
ELECTRICAL-Rough 10/28/2025 Approved ALEXANDER HANDY
HVAC-Rough 10/28/2025 Conditional Approval ALEXANDER HANDY
PLUMBING-Rough 10/28/2025 Approved ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 10/28/2025 Approved ALEXANDER HANDY
Underground Mechanical 10/28/2025 Corrections Issued ALEXANDER HANDY
Insulation 10/30/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 10/30/2025 Approved ALEXANDER HANDY
Shower Pan 10/30/2025 Approved ALEXANDER HANDY
Drywall Nailing 11/3/2025 Approved JUAN ALVARADO
Special/Order Compliance 11/18/2025 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Final 12/3/2025 Approved JEFFREY HARTLINE
Enclosure/Fence 12/3/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Final 12/3/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 12/3/2025 Approved JEFFREY HARTLINE
Smoke Detectors 12/3/2025 Approved JEFFREY HARTLINE
Underground Mechanical 12/3/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/11/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 12/11/2025 Approved GEVORK IPCHYAN
Final 12/11/2025 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 12/11/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 12/11/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved GEVORK IPCHYAN