17331 W TULSA ST 91344
Certificate Information: 17331 W TULSA ST 91344
- Application / Permit
- 23016-20000-05865
- Plan Check / Job No.
- B23VN02525
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT A PORTION OF THE (E) GARAGE AT THE (E) REAR UNIT TO A NEW ONE BEDROOM AND HALF BATHROOM AND KEEP THE GARAGE A TWO CAR GARAGE. ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2023 | JESSE ARELLANO |
| Corrections Issued | 2/28/2023 | JESSE ARELLANO |
| Issued | 3/10/2023 | APPLICANT |
| CofO in Progress | 5/22/2023 | STEVEN BACK |
| Permit Finaled | 3/26/2024 | JOHN JANSON |
| CofO Issued | 3/26/2024 | JOHN JANSON |
| Permit Finaled | 3/26/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/7/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/7/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/24/2023 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 4/24/2023 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 4/24/2023 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/24/2023 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/1/2023 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 5/1/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 5/1/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 5/5/2023 | Approved | STEVEN BACK |
| Drywall Nailing | 5/5/2023 | Approved | STEVEN BACK |
| HVAC-Rough | 5/5/2023 | Approved | STEVEN BACK |
| Insulation | 5/5/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 5/15/2023 | Approved | DAVID SCANTLIN |
| Final | 5/15/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 5/15/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 5/15/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 5/15/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 5/15/2023 | Approved | DAVID SCANTLIN |
| Final | 5/22/2023 | OK to Issue CofO | STEVEN BACK |