11217-11219 W STAGG ST 91352

Certificate Information: 11217-11219 W STAGG ST 91352

Application / Permit
23016-20000-05799
Plan Check / Job No.
B23VN02492
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 3/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/3/2023 JEROME MAGAT PALMA
Corrections Issued 3/4/2023 JEROME MAGAT PALMA
Building Plans Picked Up 3/7/2023 APPLICANT
Issued 3/21/2023 APPLICANT
CofO in Progress 10/25/2023 CHRISTOPHER ROJAS
CofO Issued 11/28/2023 RUBEN SALAS
Permit Finaled 11/28/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/9/2023 RYAN KIM
Sewer availability Cleared 3/9/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 3/13/2023 RYAN KIM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/19/2023 Approved MATTHEW NELSON
PLUMBING-Rough 4/19/2023 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 5/23/2023 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 5/23/2023 Approved MATTHEW NELSON
HVAC-Rough 5/23/2023 Approved MATTHEW NELSON
PLUMBING-Rough 5/23/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/22/2023 Approved JENNIFER RABUCHIN
Green Building Rough 6/22/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/22/2023 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 6/22/2023 Approved JENNIFER RABUCHIN
Insulation 6/26/2023 Approved WILLIAM WREN
Shower Pan 6/26/2023 Approved WILLIAM WREN
Drywall Nailing 7/5/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/5/2023 Corrections Issued MATTHEW NELSON
Interior/Exterior Lathing 7/17/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 9/13/2023 Not Ready for Inspection DAVID ANDERSON
Final 9/13/2023 Corrections Issued DAVID ANDERSON
Green Building Final 9/13/2023 Not Ready for Inspection DAVID ANDERSON
HVAC-Final 9/13/2023 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Final 9/13/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 9/13/2023 Approved DAVID ANDERSON
Final 10/24/2023 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 10/24/2023 Approved CHRISTOPHER ROJAS
HVAC-Final 10/24/2023 Approved CHRISTOPHER ROJAS