15058-15060 W GILMORE ST 91411
Certificate Information: 15058-15060 W GILMORE ST 91411
- Application / Permit
- 23016-20000-05715
- Plan Check / Job No.
- B23VN02449
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATT GARAGE INTO (N) 455 SF ACCESORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Current Status
- Issued on 4/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/4/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/11/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/24/2023 | LUISANGEL VALENZUELA |
| Issued | 4/27/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/1/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/25/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/3/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/3/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 12/3/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/20/2025 | Conditional Approval | RYAN SALAZAR |
| HVAC-Rough | 2/20/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/20/2025 | Approved | RYAN SALAZAR |
| Insulation | 4/25/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 4/25/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/29/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/29/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/14/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/14/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/14/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/18/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/26/2025 | Approved | RYAN SALAZAR |