8523 N TAMPA AVE 91324
Certificate Information: 8523 N TAMPA AVE 91324
- Application / Permit
- 23016-20000-05683
- Plan Check / Job No.
- B23VN02427
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A (N) 21'-0" x 21'-0" DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | SERGIO MUNIZ |
| Corrections Issued | 3/5/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 3/28/2023 | APPLICANT |
| Plan Check Approved | 4/21/2023 | ALFRED RAMIREZ |
| Issued | 6/7/2023 | APPLICANT |
| CofO in Progress | 7/23/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/31/2024 | JOHN JANSON |
| CofO Issued | 7/31/2024 | JOHN JANSON |
| Permit Finaled | 7/31/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/19/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | ROMAN GUTIERREZ |
| Public Works-Highway Ded. | Cleared | 4/21/2023 | ROMAN GUTIERREZ |
| Public Works-Open Permits | Cleared | 4/21/2023 | ROMAN GUTIERREZ |
| Public Works-Sewers | Cleared | 4/21/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/17/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/17/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 7/25/2023 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 7/25/2023 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/11/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/11/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Final | 10/11/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 10/11/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/11/2023 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/11/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Underground Mechanical | 10/11/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/6/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Rough | 11/6/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/20/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 11/20/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/8/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/8/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/19/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 12/19/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 12/28/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/2/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Shower Pan | 1/2/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/10/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 6/12/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 6/12/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/12/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 6/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 6/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Final | 7/22/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 7/22/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Approved | CHRIS CHRISTENSEN |