8523 N TAMPA AVE 91324

Certificate Information: 8523 N TAMPA AVE 91324

Application / Permit
23016-20000-05683
Plan Check / Job No.
B23VN02427
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO A (N) 21'-0" x 21'-0" DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 6/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2023 APPLICANT
Assigned to Plan Check Engineer 3/3/2023 SERGIO MUNIZ
Corrections Issued 3/5/2023 SERGIO MUNIZ
Building Plans Picked Up 3/28/2023 APPLICANT
Plan Check Approved 4/21/2023 ALFRED RAMIREZ
Issued 6/7/2023 APPLICANT
CofO in Progress 7/23/2024 CHRIS CHRISTENSEN
Permit Finaled 7/31/2024 JOHN JANSON
CofO Issued 7/31/2024 JOHN JANSON
Permit Finaled 7/31/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/19/2023 MEGAN GODINEZ
Sewer availability Cleared 4/19/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/21/2023 ROMAN GUTIERREZ
Public Works-Highway Ded. Cleared 4/21/2023 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 4/21/2023 ROMAN GUTIERREZ
Public Works-Sewers Cleared 4/21/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/17/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 7/25/2023 Approved HORACE FULTZ
Footing/Foundation/Slab 7/25/2023 Approved HORACE FULTZ
Interior/Exterior Lathing 8/2/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/11/2023 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/11/2023 Partial Approval CHRIS CHRISTENSEN
Final 10/11/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 10/11/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 10/11/2023 Approved CHRIS CHRISTENSEN
Smoke Detectors 10/11/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Underground Mechanical 10/11/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/6/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 11/6/2023 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/20/2023 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 11/20/2023 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/8/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/8/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/19/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 12/19/2023 Approved CHRIS CHRISTENSEN
Insulation 12/19/2023 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/28/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 1/2/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Shower Pan 1/2/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/10/2024 Approved CHRIS CHRISTENSEN
Final 6/12/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 6/12/2024 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 6/12/2024 Approved CHRIS CHRISTENSEN
Final 6/28/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 6/28/2024 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Final 7/22/2024 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 7/22/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved CHRIS CHRISTENSEN