11517 N BALBOA BLVD 91344

Certificate Information: 11517 N BALBOA BLVD 91344

Application / Permit
23016-20000-05598
Plan Check / Job No.
B23VN02402
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlam: Garage Conversion to ADU per GCS 65852.2(e)(1)(A) and WFPP
Permit Issued
Issued on 3/29/2023
Issuing Office
Current Status
CofO Issued on 12/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/7/2023 DAVID CASTILLO
Corrections Issued 3/8/2023 DAVID CASTILLO
Plan Check Approved 3/22/2023 DAVID CASTILLO
Issued 3/29/2023 APPLICANT
CofO in Progress 11/29/2023 STEVEN BACK
Permit Finaled 12/18/2023 JOHN JANSON
CofO Issued 12/18/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/14/2023 KIRK LINKLATER
Address approval Cleared 3/15/2023 MEGAN GODINEZ
Sewer availability Cleared 3/15/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/16/2023 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 3/16/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 3/16/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 3/16/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/19/2023 Approved STEVEN BACK
Footing/Foundation/Slab 4/19/2023 Approved STEVEN BACK
PLUMBING-Rough 4/19/2023 Partial Approval STEVEN BACK
Sewer 4/19/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 5/18/2023 Not Ready for Inspection HENRY KIM
MERV13>=Rough 5/18/2023 Not Ready for Inspection HENRY KIM
Special/Order Compliance 5/18/2023 Corrections Issued HENRY KIM
ELECTRICAL-Rough 6/14/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 6/14/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Not Ready for Inspection STEVEN BACK
Gas Test 6/26/2023 Not Ready for Inspection STEVEN BACK
HVAC-Rough 6/26/2023 Approved STEVEN BACK
Insulation 6/26/2023 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 6/26/2023 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 7/21/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Approved STEVEN BACK
Green Building Rough 7/21/2023 Approved STEVEN BACK
Insulation 7/21/2023 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 7/21/2023 Partial Approval STEVEN BACK
MERV13>=Rough 7/21/2023 Approved STEVEN BACK
Drywall Nailing 8/11/2023 Corrections Issued JUSTIN HAWLEY
Gas Test 8/28/2023 Partial Approval STEVEN BACK
Interior/Exterior Lathing 8/28/2023 Approved STEVEN BACK
Underground Mechanical 8/28/2023 Approved STEVEN BACK
Final 11/3/2023 Corrections Issued STEVEN BACK
Green Building Final 11/3/2023 Approved STEVEN BACK
MERV13>=Final 11/3/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Not Ready STEVEN BACK
Smoke Detectors 11/3/2023 Approved STEVEN BACK
Final 11/29/2023 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Approved STEVEN BACK
Service/Power Release 11/29/2023 Approved STEVEN BACK