8348-8350 N HILLVIEW AVE 91304

Certificate Information: 8348-8350 N HILLVIEW AVE 91304

Application / Permit
23016-20000-05500
Plan Check / Job No.
B23VN02364
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** (E) attached garage to SFD conversion to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/21/2023
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2023 APPLICANT
Assigned to Plan Check Engineer 3/3/2023 EDWIN ESPIN
Corrections Issued 3/4/2023 EDWIN ESPIN
Plan Check Approved 3/17/2023 EDWIN ESPIN
Issued 3/21/2023 APPLICANT
CofO in Progress 1/22/2024 CHRIS CHRISTENSEN
Permit Finaled 2/7/2024 JOHN JANSON
CofO Issued 2/7/2024 JOHN JANSON
Permit Finaled 2/7/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/13/2023 COLIN LOREDO
Sewer availability Cleared 3/13/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 3/16/2023 COLIN LOREDO

Contact Information

Architect Azarnoush,, Farshad; Lic. No.: NA19247       ,
Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/6/2023 Approved JOHN KIDWELL
Underground Mechanical 6/6/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/28/2023 Approved CHRIS CHRISTENSEN
Pre-Inspection 6/28/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/10/2023 Partial Approval HORACE FULTZ
Green Building Rough 7/10/2023 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 7/27/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/27/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 8/15/2023 Approved MORRIS JACKSON
Insulation 8/15/2023 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Approved CHRIS CHRISTENSEN
Shower Pan 8/24/2023 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 8/29/2023 Conditional Approval JEFFREY HARTLINE
Green Building Rough 8/29/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 8/29/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/29/2023 Approved MORRIS JACKSON
Drywall Nailing 12/29/2023 Approved MORRIS JACKSON
Final 12/29/2023 Corrections Issued MORRIS JACKSON
Green Building Final 12/29/2023 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 12/29/2023 SGSOV Not Ready MORRIS JACKSON
Smoke Detectors 12/29/2023 Approved MORRIS JACKSON
Final 1/12/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/12/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved CHRIS CHRISTENSEN
Final 1/19/2024 OK to Issue CofO CHRIS CHRISTENSEN