10947-10949 W GOSS ST 91352
Certificate Information: 10947-10949 W GOSS ST 91352
- Application / Permit
- 23016-20000-05235
- Plan Check / Job No.
- B23VN02239
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Attached 400 SQ FT Garage Conversion to ADU per GCS 65852.2(e)(1)(A) and WFPP in (E) 1-Story SFD
- Permit Issued
- Issued on 8/3/2023
- Issuing Office
- Current Status
- CofO in Progress on 6/24/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | DAVID CASTILLO |
| Corrections Issued | 4/1/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/9/2023 | JASON JANGADA |
| Applicant returned to address corrections | 7/5/2023 | HANS SANTIAGO |
| Plan Check Approved | 7/12/2023 | ANDREW SANTIAGO |
| Issued | 8/3/2023 | APPLICANT |
| CofO in Progress | 6/24/2026 | DAVID ANDERSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 4/5/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2023 | NIKKI ZULUETA |
| Clean Up Green Up | Cleared | 7/11/2023 | DALIA MOKAYED |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Pre-Inspection | 2/24/2025 | Not Ready for Inspection | ROBERT GOLD |
| Footing/Foundation/Slab | 6/30/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 12/10/2025 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 1/7/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/7/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 1/7/2026 | Approved | DAVID ANDERSON |
| HVAC-Rough | 1/7/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 1/7/2026 | Approved | DAVID ANDERSON |
| Insulation | 1/23/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/23/2026 | Partial Approval | DAVID ANDERSON |
| Shower Pan | 1/23/2026 | Approved | DAVID ANDERSON |
| Drywall Nailing | 2/6/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/19/2026 | Approved | DAVID ANDERSON |
| Final | 5/8/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 5/8/2026 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 5/8/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 6/1/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 6/1/2026 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 6/1/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 6/8/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 6/8/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 6/8/2026 | Approved | DAVID ANDERSON |
| Final | 6/9/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 6/9/2026 | Approved | DAVID ANDERSON |
| Service/Power Release | 6/9/2026 | Corrections Issued | DAVID ANDERSON |
| Smoke Detectors | 6/9/2026 | Approved | DAVID ANDERSON |
| Final | 6/23/2026 | OK to Issue CofO | DAVID ANDERSON |