1929 W PICO BLVD 90006
Certificate Information: 1929 W PICO BLVD 90006
- Application / Permit
- 23016-20000-05195
- Plan Check / Job No.
- B23VN02188
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Charter School - high school
- Work Description
- TENANT IMPROVEMENT TO (E) 2-STORY CHARTER HIGH SCHOOL UNDER CPC-2015-2289-CU-ZAA-F: CREATE (3) NEW OFFICE SPACES (580SF), ADD FIXED SEATING IN LOBBY AREAS, ADD (N) SECURITY GATE, ADD (N) CLOSETS, REMODEL (1) CLASSROOM (NO CHANGE TO ENROLLMENT, PARKING OR EXTERIOR OF BLDG) [EXISTING NFPA-13 FIRE SPRINKLERS THROUGHOUT]
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/18/2023
Permit Application Status History
| Submitted | 2/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/28/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/2/2023 | STEVEN KIM |
| Building Plans Picked Up | 3/6/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 4/6/2023 | APPLICANT |
| Applicant returned to address corrections | 5/2/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/19/2023 | NILOOFAR MEHRAIN |
| Issued | 6/2/2023 | APPLICANT |
| Permit Finaled-Status Void | 12/7/2023 | JEROME BLACKWOOD |
| Permit Finaled | 12/7/2023 | JEROME BLACKWOOD |
| Re-Activate Permit | 12/15/2023 | JEROME BLACKWOOD |
Permit Application Clearance Information
| CPC | Cleared | 3/23/2023 | MAXFIELD VERMY |
| DAS Clearance | Cleared | 4/14/2023 | NILOOFAR MEHRAIN |
| Fire Marshal Fire Life Safety | Cleared | 5/11/2023 | MENOA AGHAJANI |
Contact Information
| Contractor | Satoh Brothers International Inc; Lic. No.: 743636-B | 19750 S VERMONT AVE SUITE 100 TORRANCE, CA 90502 |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Pre-Inspection | 6/12/2023 | Partial Inspection | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 6/15/2023 | Partial Approval | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 6/15/2023 | Partial Approval | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Corrections Issued | KATY RAMIREZ |
| Light Gage Steel Frame | 6/30/2023 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 6/30/2023 | Partial Approval | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Partial Approval | RAMAZANALI ALMASI |
| Deputy Drilled-In Anchors | 7/13/2023 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 7/13/2023 | Approved | RAMAZANALI ALMASI |
| Pre-Inspection | 7/18/2023 | Partial Approval | RAMAZANALI ALMASI |
| Wall Anchors | 7/18/2023 | Partial Approval | RAMAZANALI ALMASI |
| T-Bar Ceiling | 7/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| T-Bar Ceiling | 8/4/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| T-Bar Ceiling | 8/5/2023 | Corrections Issued | KATY RAMIREZ |
| T-Bar Ceiling | 8/5/2023 | Off-Hour Fees Due | |
| T-Bar Ceiling | 8/7/2023 | Corrections Issued | KATY RAMIREZ |
| Final | 11/30/2023 | Corrections Issued | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Ready | JEROME BLACKWOOD |
| Smoke Detectors | 11/30/2023 | Approved | JEROME BLACKWOOD |
| Final | 12/7/2023 | Permit Finaled | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV Approved | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | JEROME BLACKWOOD |