1442 S ALVIRA ST 90035
Certificate Information: 1442 S ALVIRA ST 90035
- Application / Permit
- 23016-20000-04699
- Plan Check / Job No.
- B23VN02046
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE / STORAGE ROOM / LAUNDRY ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/7/2023
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 2/23/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/24/2023 | APPLICANT |
| Plan Check Approved | 9/7/2023 | ALEC MOUSAKHANIAN |
| Issued | 9/7/2023 | APPLICANT |
| CofO in Progress | 5/13/2026 | WILLIAM MICHALAK |
| Permit Finaled | 5/19/2026 | CLAUDIO MORENO |
| CofO Issued | 5/19/2026 | CLAUDIO MORENO |
| Permit Finaled | 5/19/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/6/2023 | JEANIE LAM |
| Miscellaneous | Cleared | 8/22/2023 | ALBERT TAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/7/2023 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 12/7/2023 | Corrections Issued | WILLIAM MICHALAK |
| Wood Frame | 4/19/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 8/20/2024 | Corrections Issued | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 8/20/2024 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Rough | 8/20/2024 | Corrections Issued | WILLIAM MICHALAK |
| METHANE-Rough | 8/20/2024 | Approved | WILLIAM MICHALAK |
| PLUMBING-Rough | 8/20/2024 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 10/29/2024 | Approved | WILLIAM MICHALAK |
| HVAC-Rough | 10/29/2024 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 12/18/2024 | Approved | WILLIAM MICHALAK |
| Insulation | 12/18/2024 | Approved | WILLIAM MICHALAK |
| Shower Pan | 12/18/2024 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 12/19/2024 | No Access for Inspection | WILLIAM MICHALAK |
| Insulation | 12/19/2024 | No Access for Inspection | WILLIAM MICHALAK |
| Shower Pan | 12/19/2024 | No Access for Inspection | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 10/7/2025 | Approved | WILLIAM MICHALAK |
| Final | 10/7/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| Gas Test | 10/7/2025 | Approved | WILLIAM MICHALAK |
| Green Building Final | 10/7/2025 | Approved | WILLIAM MICHALAK |
| Green Building Rough | 10/7/2025 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Not Ready | WILLIAM MICHALAK |
| Service/Power Release | 10/7/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| Smoke Detectors | 10/7/2025 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Final | 10/24/2025 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Final | 10/24/2025 | Approved | WILLIAM MICHALAK |
| Service/Power Release | 10/31/2025 | Approved | WILLIAM MICHALAK |
| Final | 2/10/2026 | Corrections Issued | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Not Ready | WILLIAM MICHALAK |
| Final | 2/27/2026 | Conditional Approval | LUIS CORRAL |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Approved | LUIS CORRAL |
| Final | 5/13/2026 | OK to Issue CofO | WILLIAM MICHALAK |