1442 S ALVIRA ST 90035

Certificate Information: 1442 S ALVIRA ST 90035

Application / Permit
23016-20000-04699
Plan Check / Job No.
B23VN02046
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE / STORAGE ROOM / LAUNDRY ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/7/2023
Issuing Office
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 JEROME MAGAT PALMA
Corrections Issued 2/23/2023 JEROME MAGAT PALMA
Building Plans Picked Up 2/24/2023 APPLICANT
Plan Check Approved 9/7/2023 ALEC MOUSAKHANIAN
Issued 9/7/2023 APPLICANT
CofO in Progress 5/13/2026 WILLIAM MICHALAK
Permit Finaled 5/19/2026 CLAUDIO MORENO
CofO Issued 5/19/2026 CLAUDIO MORENO
Permit Finaled 5/19/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 3/6/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/6/2023 JEANIE LAM
Sewer availability Cleared 3/6/2023 JEANIE LAM
Miscellaneous Cleared 8/22/2023 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/7/2023 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 12/7/2023 Corrections Issued WILLIAM MICHALAK
Wood Frame 4/19/2024 Not Ready for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 8/20/2024 Corrections Issued WILLIAM MICHALAK
ELECTRICAL-Rough 8/20/2024 Corrections Issued WILLIAM MICHALAK
Green Building Rough 8/20/2024 Corrections Issued WILLIAM MICHALAK
METHANE-Rough 8/20/2024 Approved WILLIAM MICHALAK
PLUMBING-Rough 8/20/2024 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 10/29/2024 Approved WILLIAM MICHALAK
HVAC-Rough 10/29/2024 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 12/18/2024 Approved WILLIAM MICHALAK
Insulation 12/18/2024 Approved WILLIAM MICHALAK
Shower Pan 12/18/2024 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 12/19/2024 No Access for Inspection WILLIAM MICHALAK
Insulation 12/19/2024 No Access for Inspection WILLIAM MICHALAK
Shower Pan 12/19/2024 No Access for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 10/7/2025 Approved WILLIAM MICHALAK
Final 10/7/2025 Not Ready for Inspection WILLIAM MICHALAK
Gas Test 10/7/2025 Approved WILLIAM MICHALAK
Green Building Final 10/7/2025 Approved WILLIAM MICHALAK
Green Building Rough 10/7/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 10/7/2025 SGSOV Not Ready WILLIAM MICHALAK
Service/Power Release 10/7/2025 Not Ready for Inspection WILLIAM MICHALAK
Smoke Detectors 10/7/2025 Approved WILLIAM MICHALAK
ELECTRICAL-Final 10/24/2025 Corrections Issued WILLIAM MICHALAK
PLUMBING-Final 10/24/2025 Approved WILLIAM MICHALAK
Service/Power Release 10/31/2025 Approved WILLIAM MICHALAK
Final 2/10/2026 Corrections Issued WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Not Ready WILLIAM MICHALAK
Final 2/27/2026 Conditional Approval LUIS CORRAL
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Approved LUIS CORRAL
Final 5/13/2026 OK to Issue CofO WILLIAM MICHALAK