3363 N TARECO DR 90068

Certificate Information: 3363 N TARECO DR 90068

Application / Permit
23016-20000-04262
Plan Check / Job No.
B23VN01859
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR REMODEL AT FIRST FLOOR OF EXISTING THREE STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. WORK TO INCLUDE REMOVING LOAD BEARING WALL, CREATE LAUNDRY ROOM INSTEAD OF KITCHEN AND REMOVE BEDROOM TO RELOCATE EXISTING BATHROOM - PER ENGINEER
Permit Issued
Issued on 6/23/2023
Issuing Office
Valley
Current Status
Permit Finaled on 1/18/2024

Permit Application Status History

Submitted 2/14/2023 APPLICANT
Assigned to Plan Check Engineer 2/17/2023 HAYATO TSUCHIYA
Corrections Issued 2/18/2023 HAYATO TSUCHIYA
Building Plans Picked Up 2/22/2023 APPLICANT
Applicant returned to address corrections 6/15/2023 LUISANGEL VALENZUELA
Issued 6/23/2023 APPLICANT
Permit Finaled 1/17/2024 BRIAN SULLIVAN

Permit Application Clearance Information

Specific Plan Cleared 5/4/2023 OLGA AYALA

Contact Information

Contractor Sb Construction & Remodeling Inc; Lic. No.: 1061509-B 6200 HOLLYWOOD BLVD 2540      LOS ANGELES, CA 90028
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/12/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 7/13/2023 Partial Approval STUART CHAPMAN
Sewer 7/13/2023 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 7/24/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 7/24/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 8/14/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 8/14/2023 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 8/14/2023 Approved BRIAN SULLIVAN
PLUMBING-Rough 8/14/2023 Corrections Issued BRIAN SULLIVAN
Wood Frame 8/14/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 8/17/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 8/17/2023 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 8/17/2023 Approved BRIAN SULLIVAN
Insulation 8/22/2023 Approved BRIAN SULLIVAN
Shower Pan 8/22/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/5/2023 Approved BRIAN SULLIVAN
Final 1/3/2024 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved STUART CHAPMAN
Smoke Detectors 1/3/2024 Approved STUART CHAPMAN
Final 1/17/2024 Permit Finaled BRIAN SULLIVAN
PLUMBING-Final 1/17/2024 Approved BRIAN SULLIVAN