5546-5548 N PONCE AVE 91367

Certificate Information: 5546-5548 N PONCE AVE 91367

Application / Permit
23016-20000-04061
Plan Check / Job No.
B23VN01820
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
eplan: CONVERT (E) 20'-8" x 24'-4" ATTACHED GARAGE TO JADU PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2023 APPLICANT
Assigned to Plan Check Engineer 2/24/2023 ISIS ARGUETA
Corrections Issued 2/27/2023 ISIS ARGUETA
Applicant returned to address corrections 4/11/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 4/15/2023 MIROOSH KHACHATOORIAN
Issued 4/17/2023 APPLICANT
CofO in Progress 2/20/2024 TROY SANDERS
Permit Finaled 3/6/2024 JOHN JANSON
CofO Issued 3/6/2024 JOHN JANSON
Permit Finaled 3/6/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/1/2023 RYAN KIM
Sewer availability Cleared 3/1/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 3/2/2023 RYAN KIM
Grading Pre-Inspection Cleared 3/31/2023 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/27/2023 Conditional Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 6/30/2023 Approved TROY SANDERS
Footing/Foundation/Slab 6/30/2023 Approved TROY SANDERS
PLUMBING-Rough 6/30/2023 Approved TROY SANDERS
PLUMBING-Rough 7/19/2023 Not Ready for Inspection MORRIS JACKSON
Wood Frame 7/19/2023 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 8/22/2023 Partial Approval TROY SANDERS
ELECTRICAL-Rough 8/22/2023 Approved TROY SANDERS
PLUMBING-Rough 8/22/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 8/23/2023 Approved TROY SANDERS
ELECTRICAL-Rough 8/23/2023 Approved TROY SANDERS
PLUMBING-Rough 8/23/2023 Approved TROY SANDERS
Wood Frame 8/23/2023 Approved TROY SANDERS
ELECTRICAL-Rough 9/20/2023 Approved TROY SANDERS
HVAC-Rough 9/20/2023 Approved TROY SANDERS
HVAC-Rough 10/18/2023 Approved TROY SANDERS
Insulation 10/23/2023 Approved TROY SANDERS
Interior/Exterior Lathing 10/23/2023 Partial Approval TROY SANDERS
Drywall Nailing 10/25/2023 Approved TROY SANDERS
Drywall Nailing 10/26/2023 Approved TROY SANDERS
Interior/Exterior Lathing 11/2/2023 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 11/3/2023 Partial Approval TROY SANDERS
Final 1/25/2024 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 1/25/2024 Approved TROY SANDERS
Final 2/16/2024 OK to Issue CofO TROY SANDERS