10408 N NEWHOME AVE 91040
Certificate Information: 10408 N NEWHOME AVE 91040
- Application / Permit
- 23016-20000-04035
- Plan Check / Job No.
- B23VN01803
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE THE (E) PATIO STRUCTURE.
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/13/2023 | MOHAMMAD ESMAILI |
| Issued | 2/14/2023 | APPLICANT |
| CofO in Progress | 11/8/2023 | DAVID ANDERSON |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/14/2023 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/27/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 2/27/2023 | Approved | DAVID ANDERSON |
| Pre-Inspection | 2/27/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Partial Approval | DAVID ANDERSON |
| Insulation | 3/22/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/29/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/29/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/2/2023 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/2/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 5/2/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/17/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 5/17/2023 | Approved | DAVID ANDERSON |
| Insulation | 5/24/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/24/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Drywall Nailing | 6/1/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/1/2023 | Approved | DAVID ANDERSON |
| Final | 10/31/2023 | Corrections Issued | DAVID ANDERSON |
| Smoke Detectors | 10/31/2023 | Approved | DAVID ANDERSON |
| Final | 11/6/2023 | OK to Issue CofO | DAVID ANDERSON |