8409-8411 N BRIMFIELD AVE 91402

Certificate Information: 8409-8411 N BRIMFIELD AVE 91402

Application / Permit
23016-20000-04005
Plan Check / Job No.
B23VN01790
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATT. GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/14/2023
Issuing Office
Current Status
CofO Issued on 8/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2023 APPLICANT
Assigned to Plan Check Engineer 2/17/2023 SERGIO MUNIZ
Corrections Issued 2/18/2023 SERGIO MUNIZ
Building Plans Picked Up 2/21/2023 APPLICANT
Applicant returned to address corrections 11/9/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 11/14/2023 ANGELICA MARTINEZ
Issued 11/14/2023 APPLICANT
CofO in Progress 8/23/2024 VINCENT HANLEY
CofO Issued 8/31/2024 DANIEL ORRANTE
Permit Finaled 8/31/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/23/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 2/23/2023 FERNANDO GIL
Sewer availability Cleared 2/23/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/19/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/26/2024 Approved KIRK SANDERS
Underground Mechanical 3/26/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 4/22/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 4/22/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/26/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 4/26/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 4/26/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 4/30/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 4/30/2024 Approved KIRK SANDERS
Green Building Rough 4/30/2024 Approved KIRK SANDERS
HVAC-Rough 4/30/2024 Approved KIRK SANDERS
Insulation 5/2/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 5/9/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Approved KIRK SANDERS
Drywall Nailing 5/14/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/20/2024 Approved VINCENT HANLEY
Shower Pan 5/20/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 6/28/2024 Corrections Issued VINCENT HANLEY
Final 6/28/2024 Corrections Issued VINCENT HANLEY
Green Building Final 6/28/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Ready VINCENT HANLEY
ELECTRICAL-Final 8/7/2024 Approved VINCENT HANLEY
Final 8/7/2024 Partial Approval VINCENT HANLEY
Green Building Rough 8/7/2024 Approved VINCENT HANLEY
HVAC-Final 8/7/2024 Approved VINCENT HANLEY
PLUMBING-Final 8/7/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 8/7/2024 Approved VINCENT HANLEY
Smoke Detectors 8/7/2024 Approved VINCENT HANLEY
Final 8/23/2024 OK to Issue CofO VINCENT HANLEY