8360-8362 W APPERSON ST 91040

Certificate Information: 8360-8362 W APPERSON ST 91040

Application / Permit
23016-20000-03927
Plan Check / Job No.
B23VN01753
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING 646 SQ FT ATTACHED 3-CAR GARAGE INTO A.D.U. PER STATE LAW
Permit Issued
Issued on 4/28/2023
Issuing Office
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2023 APPLICANT
Assigned to Plan Check Engineer 2/21/2023 WEIJIAN HUANG
Corrections Issued 2/22/2023 WEIJIAN HUANG
Plan Check Approved 3/21/2023 JOSEPH RAFOLS
Issued 4/28/2023 APPLICANT
CofO in Progress 12/6/2024 DAVID ANDERSON
Permit Finaled 1/9/2025 RUBEN SALAS
Permit Finaled 1/9/2025 RUBEN SALAS
CofO Issued 1/9/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/14/2023 MEGAN GODINEZ
Sewer availability Cleared 3/14/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/20/2023 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 3/20/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 3/20/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 3/20/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/11/2023 Approved DAVID ANDERSON
Underground Mechanical 11/21/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 11/30/2023 Approved DAVID ANDERSON
Sewer 11/30/2023 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 12/7/2023 Conditional Approval JUAN VALENZUELA
Pre-Inspection 1/31/2024 Approved DAVID ANDERSON
ELECTRICAL-Final 2/9/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 2/9/2024 Approved WILLIAM WREN
HVAC-Rough 2/9/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 2/9/2024 Approved WILLIAM WREN
Footing/Foundation/Slab 2/13/2024 Approved DAVID ANDERSON
HVAC-Rough 2/13/2024 Approved DAVID ANDERSON
Underground Mechanical 2/13/2024 Partial Approval DAVID ANDERSON
Underground Mechanical 2/14/2024 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 2/20/2024 Approved DAVID ANDERSON
Insulation 3/1/2024 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 3/1/2024 Not Ready for Inspection DAVID ANDERSON
Special/Order Compliance 3/1/2024 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 5/7/2024 Corrections Issued DAVID ANDERSON
Insulation 5/7/2024 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 5/7/2024 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 5/15/2024 Approved DAVID ANDERSON
Insulation 5/15/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/15/2024 Partial Approval DAVID ANDERSON
Drywall Nailing 5/31/2024 Approved DAVID ANDERSON
Shower Pan 8/27/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/25/2024 Approved DAVID ANDERSON
Final 11/18/2024 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 11/18/2024 Not Ready for Inspection DAVID ANDERSON
Final 11/26/2024 Corrections Issued DAVID ANDERSON
Smoke Detectors 11/26/2024 Approved DAVID ANDERSON
Final 12/5/2024 OK to Issue CofO DAVID ANDERSON