8418-8422 N GLORIA AVE 91343
Certificate Information: 8418-8422 N GLORIA AVE 91343
- Application / Permit
- 23016-20000-03925
- Plan Check / Job No.
- B23VN01752
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE TO JADU PER GCS 65852.2(e)(1)(A). WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | ISIS ARGUETA |
| Corrections Issued | 2/27/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 3/23/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 4/10/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/24/2023 | ISIS ARGUETA |
| Issued | 5/24/2023 | APPLICANT |
| CofO in Progress | 8/4/2023 | RAUL OLAGI |
| Permit Finaled | 8/23/2023 | RUBEN SALAS |
| Permit Finaled | 8/23/2023 | RUBEN SALAS |
| CofO Issued | 8/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/1/2023 | DANIEL CORONADO |
| Address approval | Cleared | 3/2/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 3/2/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 3/3/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 3/3/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 3/3/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 6/8/2023 | Approved | RAUL OLAGI |
| Pre-Inspection | 6/8/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 6/28/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/28/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/28/2023 | Approved | RAUL OLAGI |
| Sewer | 6/28/2023 | Approved | RAUL OLAGI |
| Insulation | 6/30/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/30/2023 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 7/10/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/10/2023 | Approved | RAUL OLAGI |
| Shower Pan | 7/10/2023 | Approved | RAUL OLAGI |
| Final | 8/4/2023 | OK to Issue CofO | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 8/4/2023 | Approved | RAUL OLAGI |