16141 W HART ST 91406

Certificate Information: 16141 W HART ST 91406

Application / Permit
23016-20000-03887
Plan Check / Job No.
B23VN01737
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
Tenant improvement to convert a portion of existing manufacturing warehouse space into new H4 storage space.
Permit Issued
Issued on 4/26/2023
Issuing Office
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2023 APPLICANT
Assigned to Plan Check Engineer 2/21/2023 PINANK PATEL
Corrections Issued 2/22/2023 PINANK PATEL
Plan Check Approved 4/20/2023 PINANK PATEL
Issued 4/26/2023 APPLICANT
CofO in Progress 7/15/2024 STEVEN LEVITT
Permit Finaled 7/16/2024 JEFFREY DURAN
CofO Issued 7/16/2024 JEFFREY DURAN
Permit Finaled 7/16/2024 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 2/24/2023 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 2/27/2023 CARLOS AGUILERA
Sewer availability Cleared 2/27/2023 CARLOS AGUILERA
Fire Marshal Fire Life Safety Cleared 4/18/2023 WILLIAM JOHNS

Contact Information

Contractor Go Green Remodeling & Repair Inc; Lic. No.: 957317-B       ,
Contractor Milanco Building Group; Lic. No.: 957317-B       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2023 Approved STEVEN LEVITT
Footing/Foundation/Slab 7/17/2023 Approved STEVEN LEVITT
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Approved STEVEN LEVITT
Light Gage Steel Frame 7/24/2023 Approved STEVEN LEVITT
Drywall Nailing 7/26/2023 Partial Approval STEVEN LEVITT
Drywall Nailing 7/28/2023 Approved STEVEN LEVITT
Structural Steel Frame 8/14/2023 Approved STEVEN LEVITT
Final 9/26/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 9/26/2023 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 9/26/2023 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 9/28/2023 Corrections Issued JEFFREY FULTON
Final 10/3/2023 Not Ready for Inspection STEVEN LEVITT
Reinforced Masonry Frame 10/3/2023 Not Ready for Inspection STEVEN LEVITT
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Not Ready STEVEN LEVITT
Smoke Detectors 10/3/2023 Not Ready for Inspection STEVEN LEVITT
Final 10/25/2023 OK to Issue CofO STEVEN LEVITT
Reinforced Masonry Frame 10/25/2023 Approved STEVEN LEVITT
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved STEVEN LEVITT
Smoke Detectors 10/25/2023 Approved STEVEN LEVITT