751 N VIA DE LA PAZ 90272

Certificate Information: 751 N VIA DE LA PAZ 90272

Application / Permit
23016-20000-03841
Plan Check / Job No.
B23VN01708
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 24'-4" X 17'-3" DETACHED GARAGE TO ADU PER LAMC 12.22A33 (C) & (D) - PER ENGINEER
Permit Issued
Issued on 3/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2023 APPLICANT
Assigned to Plan Check Engineer 2/17/2023 SERGIO MUNIZ
Corrections Issued 2/19/2023 SERGIO MUNIZ
Building Plans Picked Up 2/27/2023 APPLICANT
Issued 3/1/2023 APPLICANT
CofO in Progress 3/21/2024 EVAN COOPER
CofO Issued 4/10/2024 DANIEL ORRANTE
Permit Finaled 4/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/22/2023 JENSON LEE
Sewer availability Cleared 2/22/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 2/23/2023 JENSON LEE
ZA Case Cleared 2/23/2023 KENTON TRINH
Construction near power lines Cleared 2/24/2023 WALTER RAMIREZ
Construction within easement Cleared 2/24/2023 WALTER RAMIREZ

Contact Information

Contractor J G Builders Inc; Lic. No.: 1049536-B 4418 LA MADERA AVENUE      EL MONTE, CA 91732
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/18/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/25/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 5/25/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 6/9/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 6/23/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 6/23/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/10/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 9/7/2023 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 9/8/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 9/8/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Partial Approval EVAN COOPER
Green Building Rough 9/8/2023 Not Ready for Inspection EVAN COOPER
Insulation 9/8/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 9/8/2023 Approved EVAN COOPER
Insulation 9/19/2023 Corrections Issued EVAN COOPER
Insulation 9/25/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Approved EVAN COOPER
Insulation 9/28/2023 Approved EVAN COOPER
Interior/Exterior Lathing 9/28/2023 Partial Approval EVAN COOPER
Drywall Nailing 10/5/2023 Approved EVAN COOPER
Interior/Exterior Lathing 10/5/2023 Partial Approval EVAN COOPER
Shower Pan 12/21/2023 Approved EVAN COOPER
Sewer 3/5/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 3/19/2024 Approved ARAM AVEDISIAN
Final 3/19/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/19/2024 Approved ARAM AVEDISIAN
Green Building Rough 3/19/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 3/19/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/21/2024 Approved EVAN COOPER
Final 3/21/2024 OK to Issue CofO EVAN COOPER
HVAC-Final 3/21/2024 Approved EVAN COOPER
PLUMBING-Final 3/21/2024 Approved EVAN COOPER