18300 W SHERMAN WAY 91335
Certificate Information: 18300 W SHERMAN WAY 91335
- Application / Permit
- 23016-20000-03787
- Plan Check / Job No.
- B23VN01667
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- ePlan: Full building Tenant improvement within including new partitions, ceiling, power, and finishes. Two new accessible single user restroom. Change of use from retail (M) to dental office (B).
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | ERIC WONG |
| Corrections Issued | 2/25/2023 | ERIC WONG |
| Quality Review Completed | 3/1/2023 | PETER KIM |
| Plan Check Approved | 5/4/2023 | ERIC WONG |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 3/4/2024 | BRIAN KELLY |
| Permit Finaled | 3/8/2024 | JEFFREY DURAN |
| CofO Issued | 3/8/2024 | JEFFREY DURAN |
| Permit Finaled | 3/8/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 3/9/2023 | COLIN LOREDO |
| "D" conditions | Cleared | 3/10/2023 | RUBEN VASQUEZ |
| Comm Cor/Mini-Mall | Cleared | 3/10/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/10/2023 | RUBEN VASQUEZ |
| Comm Cor/Mini-Mall | Cleared | 3/21/2023 | DANIEL CORONADO |
| "Q" conditions | Cleared | 3/24/2023 | LAURA FRAZIN-STEELE |
| Supp. Use District POD/CDO/TDO | Cleared | 3/24/2023 | LAURA FRAZIN-STEELE |
| ZI | Cleared | 3/24/2023 | LAURA FRAZIN-STEELE |
| Green Code | Cleared | 4/18/2023 | Ricardo Ramirez Solis |
| DAS Clearance | Cleared | 5/4/2023 | Ricardo Ramirez Solis |
Contact Information
| Architect | Kamus,, John Howard; Lic. No.: C20397 | 1965 YOSEMITE AVE SUITE #205 SIMI VALLEY, CA 93063 |
| Contractor | Interscope Construction Management Ca Llc; Lic. No.: 1097606-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2023 | No Access for Inspection | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 5/31/2023 | Approved | BRIAN KELLY |
| Footing/Foundation/Slab | 5/31/2023 | Approved | BRIAN KELLY |
| Light Gage Steel Frame | 6/12/2023 | Partial Approval | BRIAN KELLY |
| Insulation | 6/15/2023 | Corrections Issued | BRIAN KELLY |
| Insulation | 6/21/2023 | Approved | BRIAN KELLY |
| Drywall Nailing | 6/23/2023 | Approved | BRIAN KELLY |
| T-Bar Ceiling | 7/7/2023 | Partial Approval | BRIAN KELLY |
| Final | 8/8/2023 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 8/8/2023 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 8/8/2023 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 8/8/2023 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 8/8/2023 | Not Ready for Inspection | BRIAN KELLY |
| Final | 8/14/2023 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 8/14/2023 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 8/14/2023 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 8/14/2023 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 8/14/2023 | Approved | BRIAN KELLY |
| Final | 1/9/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 1/9/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 1/9/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 1/17/2024 | Partial Inspection | BRIAN KELLY |
| Green Building Final | 1/17/2024 | Partial Approval | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 1/17/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 2/15/2024 | Partial Inspection | BRIAN KELLY |
| Final | 3/4/2024 | OK to Issue CofO | BRIAN KELLY |
| Green Building Final | 3/4/2024 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 3/4/2024 | Approved | BRIAN KELLY |