8349-8351 N MAYNARD AVE 91304
Certificate Information: 8349-8351 N MAYNARD AVE 91304
- Application / Permit
- 23016-20000-03779
- Plan Check / Job No.
- B23VN01663
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE & PORTION OF (E) SFD TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.2. MAJOR INTERIOR REMODEL TO (E) SFD WITH REMOVAL OF WALL BETWEEEN KITCHEN & LIVING ROOM
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Corrected on 2/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 2/18/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 3/11/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/17/2023 | ALEC MOUSAKHANIAN |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 1/30/2024 | CHRIS CHRISTENSEN |
| Re-Activate Permit | 2/15/2024 | JOHN JANSON |
| CofO Issued-Status Void | 2/15/2024 | JOHN JANSON |
| Permit Finaled-Status Void | 2/15/2024 | JOHN JANSON |
| Permit Finaled | 2/15/2024 | JOHN JANSON |
| CofO Corrected | 2/15/2024 | JOHN JANSON |
| Permit Finaled | 2/15/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2023 | MATTHEW MAHLEBASHIAN |
| Roof/Waste drainage to street | Cleared | 2/24/2023 | MATTHEW MAHLEBASHIAN |
| Sewer availability | Cleared | 2/24/2023 | MATTHEW MAHLEBASHIAN |
| Grading Pre-Inspection | Cleared | 3/6/2023 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/22/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/24/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/24/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/31/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/31/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/10/2023 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/10/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/10/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/10/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/13/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 4/13/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 4/13/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 4/13/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/13/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 4/18/2023 | Partial Approval | JUSTIN HAWLEY |
| PLUMBING-Rough | 4/18/2023 | Corrections Issued | DAVID SANDOVAL |
| Drywall Nailing | 4/24/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/24/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/27/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/27/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 6/27/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/27/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 7/11/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |