9216-9218 N CAYUGA AVE 91352
Certificate Information: 9216-9218 N CAYUGA AVE 91352
- Application / Permit
- 23016-20000-03750
- Plan Check / Job No.
- B23VN01650
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A) AND (N) LAUNDRY, ALL WORK PER ENG.
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | JESSE ARELLANO |
| Corrections Issued | 2/18/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 2/21/2023 | APPLICANT |
| Plan Check Approved | 3/9/2023 | LUISANGEL VALENZUELA |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 5/17/2023 | MATTHEW NELSON |
| Permit Finaled | 5/18/2023 | MICHAEL SMITH |
| CofO Issued | 5/18/2023 | MICHAEL SMITH |
| Permit Finaled | 5/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/25/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/20/2023 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/23/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/29/2023 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 3/29/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/3/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 4/3/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 4/4/2023 | Approved | JOHN COLEMAN |
| HVAC-Rough | 4/4/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 4/4/2023 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 4/11/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 4/12/2023 | Approved | MATTHEW NELSON |
| Insulation | 4/17/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/17/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/20/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 4/20/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/26/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | MATTHEW NELSON |
| Final | 5/11/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 5/11/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/11/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/11/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/16/2023 | Approved | MATTHEW NELSON |
| Service/Power Release | 5/16/2023 | Approved | MATTHEW NELSON |
| Final | 5/17/2023 | OK to Issue CofO | MATTHEW NELSON |