13476 W POLK ST 91342
Certificate Information: 13476 W POLK ST 91342
- Application / Permit
- 23016-20000-03749
- Plan Check / Job No.
- B23VN01649
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Renovation of (E) SFD. Scope of work to include repair of fire-damaged structural framing, relocate, dining room, living room, and kitchen, new windows and doors, new interior walls, new roof, new interior finish, and new kitchen countertops and cabinets. See comments.
- Permit Issued
- Issued on 12/1/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2023 | JASON JANGADA |
| Corrections Issued | 2/20/2023 | JASON JANGADA |
| Applicant returned to address corrections | 8/11/2023 | JASON JANGADA |
| Applicant returned to address corrections | 9/1/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 11/8/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 11/13/2023 | ARSALAN SHABESTARI |
| Issued | 12/1/2023 | APPLICANT |
| Permit Finaled | 6/11/2025 | KEVIN BERBERYAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/24/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 10/12/2023 | ALEXANDER HELFER |
| Miscellaneous | Cleared | 10/14/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 11/1/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/5/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 3/5/2025 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/5/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 3/5/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/5/2025 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 4/15/2025 | Conditional Approval | RAUL OLAGI |
| Final | 6/11/2025 | Permit Finaled | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 6/11/2025 | Approved | KEVIN BERBERYAN |