645 N TIGERTAIL ROAD 90049
Certificate Information: 645 N TIGERTAIL ROAD 90049
- Application / Permit
- 23016-20000-03151
- Plan Check / Job No.
- B23VN01419
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- REMODEL OF (E) ACCESSORY LIVING QUARTER, RE-ROOFING. NO ADDITION
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 11/21/2024
Permit Application Status History
| Submitted | 2/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/14/2023 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 2/23/2023 | APPLICANT |
| Plan Check Approved | 4/21/2023 | MOHAMMAD ESMAILI |
| Issued | 12/5/2023 | APPLICANT |
| Permit Finaled | 11/20/2024 | KEVIN SARGSYAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | The Resto Group; Lic. No.: 898290-B | 311 N ROBERTSON SUITE 732 BEVERLY HILLS, CA 90211 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/22/2024 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/18/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/18/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/18/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/20/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 3/20/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 3/26/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/26/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/29/2024 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 4/9/2024 | Approved | KEVIN SARGSYAN |
| Insulation | 4/10/2024 | Partial Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 4/23/2024 | Approved | ARAM AVEDISIAN |
| Gas Test | 6/28/2024 | Partial Approval | KENNETH NAGLE |
| Shower Pan | 6/28/2024 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 9/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| Final | 9/6/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 9/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 9/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 9/6/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 9/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 9/17/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/22/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/14/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/20/2024 | Approved | KEVIN SARGSYAN |
| Final | 11/20/2024 | Permit Finaled | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Approved | KEVIN SARGSYAN |