645 N TIGERTAIL ROAD 90049

Certificate Information: 645 N TIGERTAIL ROAD 90049

Application / Permit
23016-20000-03151
Plan Check / Job No.
B23VN01419
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
REMODEL OF (E) ACCESSORY LIVING QUARTER, RE-ROOFING. NO ADDITION
Permit Issued
Issued on 12/5/2023
Issuing Office
Valley
Current Status
Permit Finaled on 11/21/2024

Permit Application Status History

Submitted 2/6/2023 APPLICANT
Assigned to Plan Check Engineer 2/13/2023 MOHAMMAD ESMAILI
Corrections Issued 2/14/2023 MOHAMMAD ESMAILI
Building Plans Picked Up 2/23/2023 APPLICANT
Plan Check Approved 4/21/2023 MOHAMMAD ESMAILI
Issued 12/5/2023 APPLICANT
Permit Finaled 11/20/2024 KEVIN SARGSYAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor The Resto Group; Lic. No.: 898290-B 311 N ROBERTSON SUITE 732      BEVERLY HILLS, CA 90211

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/22/2024 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 3/18/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 3/18/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 3/18/2024 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 3/20/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 3/20/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 3/26/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 3/26/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/29/2024 Partial Approval KEVIN SARGSYAN
Insulation 4/9/2024 Approved KEVIN SARGSYAN
Insulation 4/10/2024 Partial Inspection KEVIN SARGSYAN
Drywall Nailing 4/23/2024 Approved ARAM AVEDISIAN
Gas Test 6/28/2024 Partial Approval KENNETH NAGLE
Shower Pan 6/28/2024 Approved KENNETH NAGLE
ELECTRICAL-Final 9/6/2024 Corrections Issued KEVIN SARGSYAN
Final 9/6/2024 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 9/6/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 9/6/2024 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 9/6/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 9/11/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 9/17/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/22/2024 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 11/14/2024 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 11/20/2024 Approved KEVIN SARGSYAN
Final 11/20/2024 Permit Finaled KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Approved KEVIN SARGSYAN