7741 W WENTWORTH ST 91042

Certificate Information: 7741 W WENTWORTH ST 91042

Application / Permit
23016-20000-03077
Plan Check / Job No.
B23VN01377
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Convert (E) Detached Garage at rear of the lot to Accessory Dwellin Unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/24/2023
Issuing Office
Current Status
CofO Issued on 7/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2023 APPLICANT
Assigned to Plan Check Engineer 2/17/2023 EDWIN ESPIN
Corrections Issued 2/19/2023 EDWIN ESPIN
Applicant returned to address corrections 3/16/2023 EDWIN ESPIN
Applicant returned to address corrections 3/20/2023 EDWIN ESPIN
Plan Check Approved 3/23/2023 EDWIN ESPIN
Issued 3/24/2023 APPLICANT
CofO in Progress 6/25/2024 WILLIAM WREN
CofO Issued 7/22/2024 RUBEN SALAS
Permit Finaled 7/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/23/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 2/23/2023 COLIN LOREDO
Sewer availability Cleared 3/9/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 3/20/2023 KIRK LINKLATER
Tenant Habitability Plan Cleared 3/20/2023 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: NA41697       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/19/2023 Not Ready for Inspection WILLIAM WREN
Underground Mechanical 4/19/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 4/28/2023 Partial Approval WILLIAM WREN
Deputy Drilled-In Anchors 5/3/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 5/8/2023 Approved WILLIAM WREN
PLUMBING-Rough 7/27/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 8/7/2023 Approved WILLIAM WREN
HVAC-Rough 8/7/2023 Corrections Issued WILLIAM WREN
Deputy Drilled-In Anchors 8/9/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 8/14/2023 Approved WILLIAM WREN
Green Building Rough 8/14/2023 Approved WILLIAM WREN
HVAC-Rough 8/14/2023 Approved WILLIAM WREN
Insulation 8/17/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Approved WILLIAM WREN
Insulation 8/28/2023 Approved WILLIAM WREN
Drywall Nailing 9/7/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 9/7/2023 Approved WILLIAM WREN
Shower Pan 9/12/2023 Approved WILLIAM WREN
Sewer 10/2/2023 Partial Inspection WILLIAM WREN
Sewer 10/11/2023 Partial Approval WILLIAM WREN
Underground Mechanical 10/11/2023 Not Ready for Inspection WILLIAM WREN
Sewer 10/17/2023 Approved WILLIAM WREN
Gas Test 10/23/2023 Approved WILLIAM WREN
Underground Mechanical 10/23/2023 Approved WILLIAM WREN
Service/Power Release 3/28/2024 Corrections Issued WILLIAM WREN
Final 6/3/2024 Corrections Issued WILLIAM WREN
Green Building Final 6/3/2024 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 6/3/2024 SGSOV Not Ready WILLIAM WREN
Smoke Detectors 6/3/2024 Approved WILLIAM WREN
Final 6/13/2024 Corrections Issued WILLIAM WREN
Green Building Final 6/13/2024 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Approved WILLIAM WREN
Final 6/17/2024 OK to Issue CofO WILLIAM WREN