13674-13676 W WEIDNER ST 91331
Certificate Information: 13674-13676 W WEIDNER ST 91331
- Application / Permit
- 23016-20000-03046
- Plan Check / Job No.
- B23VN01363
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE AND PORTION OF (E) SINGLE-FAMILY DWELLING TO JADU PER GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 4/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 2/13/2023 | ALEC MOUSAKHANIAN |
| Building Plans Picked Up | 2/14/2023 | APPLICANT |
| Plan Check Approved | 3/24/2023 | JESSE ARELLANO |
| Issued | 4/7/2023 | APPLICANT |
| CofO in Progress | 9/3/2025 | MICHEL ABAJAN |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 3/2/2023 | NATHAN ROMINE |
| Address approval | Cleared | 3/3/2023 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/3/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/4/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/27/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/27/2024 | Approved | MICHEL ABAJAN |
| Sewer | 6/27/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/3/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/3/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/3/2024 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/3/2024 | Approved | MICHEL ABAJAN |
| Insulation | 7/18/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/18/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/24/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| Final | 7/18/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 7/18/2025 | Approved | MICHEL ABAJAN |
| Final | 8/18/2025 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | MICHEL ABAJAN |
| Final | 9/2/2025 | OK to Issue CofO | MICHEL ABAJAN |