9909-9911 N STANWIN AVE 91331

Certificate Information: 9909-9911 N STANWIN AVE 91331

Application / Permit
23016-20000-03015
Plan Check / Job No.
B23VN01355
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 19'2"x 21' ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 10/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2023 APPLICANT
Assigned to Plan Check Engineer 2/10/2023 ISIS ARGUETA
Corrections Issued 2/13/2023 ISIS ARGUETA
Building Plans Picked Up 2/17/2023 APPLICANT
Applicant returned to address corrections 3/20/2023 JESSE ARELLANO
Plan Check Approved 7/26/2023 OMAR GARNICA
Issued 10/5/2023 APPLICANT
CofO in Progress 8/8/2024 MICHEL ABAJAN
CofO Issued 8/31/2024 DANIEL ORRANTE
Permit Finaled 8/31/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/7/2023 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 6/7/2023 JOHN LIN
Sewer availability Cleared 6/7/2023 JOHN LIN
Public Works-Highway Ded. Cleared 7/13/2023 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 7/13/2023 ROMAN GUTIERREZ
Public Works-Sewers Cleared 7/13/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/17/2023 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 1/30/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/20/2024 Approved MICHEL ABAJAN
HVAC-Rough 2/20/2024 Approved MICHEL ABAJAN
Wood Frame 2/20/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 4/18/2024 Approved MICHEL ABAJAN
Green Building Rough 4/18/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/18/2024 Approved MICHEL ABAJAN
METHANE-Rough 4/18/2024 Approved MICHEL ABAJAN
Insulation 5/8/2024 Approved MICHEL ABAJAN
Drywall Nailing 5/14/2024 Approved MICHEL ABAJAN
Shower Pan 5/28/2024 Approved JOHN COLEMAN
Wood Frame 5/30/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/26/2024 Approved MICHEL ABAJAN
Final 7/26/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 7/26/2024 Approved MICHEL ABAJAN
HVAC-Final 7/26/2024 Approved MICHEL ABAJAN
PLUMBING-Final 7/26/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 7/26/2024 Approved MICHEL ABAJAN
Final 7/30/2024 Corrections Issued MICHEL ABAJAN
Final 8/8/2024 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 8/8/2024 Approved MICHEL ABAJAN