12147 N EL ORO WAY 91344

Certificate Information: 12147 N EL ORO WAY 91344

Application / Permit
23016-20000-02949
Plan Check / Job No.
B23VN01328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) detached Garage to ADU per State Law
Permit Issued
Issued on 4/18/2023
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2023 APPLICANT
Assigned to Plan Check Engineer 2/17/2023 MINA HABILI
Corrections Issued 2/21/2023 MINA HABILI
Applicant returned to address corrections 4/11/2023 MINA HABILI
Plan Check Approved 4/13/2023 MINA HABILI
Issued 4/18/2023 APPLICANT
CofO in Progress 11/7/2024 STEVEN BACK
Permit Finaled 11/13/2024 JOHN JANSON
CofO Issued 11/13/2024 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/30/2023 KIRK LINKLATER
Address approval Cleared 4/5/2023 ROMAN GUTIERREZ
Sewer availability Cleared 4/5/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/6/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2023 Corrections Issued STEVEN BACK
Rough-Elec/Plmb/HVAC 10/12/2023 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 10/27/2023 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 10/27/2023 Approved STEVEN BACK
HVAC-Rough 10/27/2023 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 10/27/2023 Not Ready for Inspection STEVEN BACK
Underground Mechanical 10/27/2023 Not Ready for Inspection STEVEN BACK
Underground Mechanical 12/26/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 1/17/2024 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 5/13/2024 Approved DAVID SCANTLIN
HVAC-Rough 5/13/2024 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Corrections Issued STEVEN BACK
PLUMBING-Rough 5/14/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 5/21/2024 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Corrections Issued STEVEN BACK
Green Building Rough 5/21/2024 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 6/12/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/12/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/12/2024 Partial Approval CHRIS CHRISTENSEN
Insulation 7/31/2024 Approved JEFFREY BULL
Drywall Nailing 8/13/2024 Approved CHRIS CHRISTENSEN
Shower Pan 8/13/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/22/2024 Approved CHRIS CHRISTENSEN
Final 10/24/2024 Corrections Issued STEVEN BACK
Green Building Final 10/24/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/24/2024 SGSOV Not Ready STEVEN BACK
Smoke Detectors 10/24/2024 Approved STEVEN BACK
Final 11/7/2024 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Approved STEVEN BACK
Service/Power Release 11/7/2024 Approved STEVEN BACK