13273 W BEAVER ST 91342

Certificate Information: 13273 W BEAVER ST 91342

Application / Permit
23016-20000-02906
Plan Check / Job No.
B23VN01312
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2023 APPLICANT
Assigned to Plan Check Engineer 2/10/2023 SERGIO MUNIZ
Corrections Issued 2/11/2023 SERGIO MUNIZ
Building Plans Picked Up 2/21/2023 APPLICANT
Plan Check Approved 3/1/2023 MOHAMMAD ESMAILI
Issued 3/1/2023 APPLICANT
CofO in Progress 1/3/2024 KEVIN BERBERYAN
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/25/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/25/2023 CARLOS AGUILERA
Sewer availability Cleared 2/25/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/5/2023 Conditional Approval ROBERT GOLD
PLUMBING-Rough 5/9/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 6/15/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 6/15/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 6/15/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/15/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/26/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 6/26/2023 Approved ARAM AVEDISIAN
HVAC-Rough 6/26/2023 Approved ARAM AVEDISIAN
Shower Pan 6/26/2023 Approved ARAM AVEDISIAN
Insulation 7/3/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/3/2023 Approved MICHEL ABAJAN
Drywall Nailing 7/13/2023 Approved MICHEL ABAJAN
Gas Test 9/26/2023 Approved KEVIN BERBERYAN
Sewer 9/26/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/26/2023 Approved KEVIN BERBERYAN
Final 12/26/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 12/26/2023 Approved KEVIN BERBERYAN
Green Building Rough 12/26/2023 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 12/26/2023 Approved KEVIN BERBERYAN
Final 1/2/2024 OK to Issue CofO KEVIN BERBERYAN