8367-8369 N HILLARY DR 91304

Certificate Information: 8367-8369 N HILLARY DR 91304

Application / Permit
23016-20000-02671
Plan Check / Job No.
B23VN01166
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Convert Attached Garage into ADU per State law and GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/23/2023
Issuing Office
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2023 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 ZAW HAN
Corrections Issued 2/10/2023 ZAW HAN
Applicant returned to address corrections 3/2/2023 VICTOR CHEN
Plan Check Approved 3/21/2023 JOSEPH RAFOLS
Issued 3/23/2023 APPLICANT
CofO in Progress 7/12/2023 CHRIS CHRISTENSEN
CofO Issued 7/31/2023 JOHN JANSON
Permit Finaled 7/31/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/13/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/13/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/13/2023 CARLOS AGUILERA
Sewer availability Cleared 2/13/2023 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/1/2023 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/3/2023 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/3/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/26/2023 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/26/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 4/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 4/26/2023 Approved CHRIS CHRISTENSEN
Sewer 4/26/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/3/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 5/3/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 5/3/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/3/2023 Partial Approval CHRIS CHRISTENSEN
Insulation 5/5/2023 Approved CHRIS CHRISTENSEN
Shower Pan 5/5/2023 Approved CHRIS CHRISTENSEN
Drywall Nailing 5/9/2023 Approved CHRIS CHRISTENSEN
Pre-Inspection 5/18/2023 Approved CHRIS CHRISTENSEN
Final 6/14/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 6/14/2023 Approved CHRIS CHRISTENSEN
Final 7/11/2023 OK to Issue CofO CHRIS CHRISTENSEN
Service/Power Release 7/11/2023 Approved CHRIS CHRISTENSEN