19034 W PLUMMER ST 91324
Certificate Information: 19034 W PLUMMER ST 91324
- Application / Permit
- 23016-20000-02524
- Plan Check / Job No.
- B23VN01112
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21' X 21'6" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/21/2023
- Issuing Office
- Current Status
- CofO Issued on 10/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | MADISON ODELL |
| Corrections Issued | 2/10/2023 | MADISON ODELL |
| Plan Check Approved | 3/7/2023 | MADISON ODELL |
| Issued | 3/21/2023 | APPLICANT |
| CofO in Progress | 10/5/2023 | JOHN KIDWELL |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
| CofO Issued | 10/6/2023 | JOHN JANSON |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/13/2023 | MATTHEW MAHLEBASHIAN |
| Address approval | Cleared | 2/14/2023 | MATTHEW MAHLEBASHIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Evolution Design & Development Inc; Lic. No.: 999377-B | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/6/2023 | Approved | SEAN HAUPT |
| Sewer | 4/6/2023 | Approved | SEAN HAUPT |
| Pre-Inspection | 4/10/2023 | No Access for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 4/10/2023 | No Access for Inspection | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/12/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 4/12/2023 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/25/2023 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/25/2023 | Approved | JUSTIN HAWLEY |
| Gas Test | 4/25/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 5/12/2023 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/22/2023 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 6/22/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 6/27/2023 | Approved | JOHN KIDWELL |
| Drywall Nailing | 7/7/2023 | Approved | JOHN KIDWELL |
| Insulation | 7/7/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/7/2023 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/31/2023 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 7/31/2023 | Approved | JOHN KIDWELL |
| Final | 9/18/2023 | Corrections Issued | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 9/18/2023 | Approved | JOHN KIDWELL |
| Final | 9/29/2023 | OK to Issue CofO | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Approved | JOHN KIDWELL |