7724 N WINNETKA AVE 91306

Certificate Information: 7724 N WINNETKA AVE 91306

Application / Permit
23016-20000-02482
Plan Check / Job No.
B23VN01087
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 17'X 19' GARAGE INTO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/30/2023
Issuing Office
Valley
Current Status
CofO in Progress on 3/6/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/30/2023 APPLICANT
Assigned to Plan Check Engineer 2/8/2023 HAYATO TSUCHIYA
Corrections Issued 2/9/2023 HAYATO TSUCHIYA
Building Plans Picked Up 2/13/2023 APPLICANT
Issued 5/30/2023 APPLICANT
CofO in Progress 3/6/2026 ALEXANDER HANDY

Permit Application Clearance Information

Address approval Cleared 3/20/2023 CARLOS AGUILERA
Sewer availability Cleared 3/20/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/21/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/6/2023 Approved ALEXANDER HANDY
Footing/Foundation/Slab 12/6/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 12/6/2023 Partial Approval ALEXANDER HANDY
Sewer 12/6/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 7/26/2024 Conditional Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 7/26/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 7/26/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 7/26/2024 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 7/26/2024 Approved ARUTYUN MADATYAN
Insulation 8/2/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 8/2/2024 Partial Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 8/23/2024 Approved ARUTYUN MADATYAN
Green Building Rough 8/23/2024 Approved ARUTYUN MADATYAN
Shower Pan 8/23/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 8/28/2024 No Access for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 9/3/2024 Approved SCOTT SOBEL
BUILDING-Rough-Frame 2/10/2026 Approved ALEXANDER HANDY
ELECTRICAL-Final 2/10/2026 Not Ready for Inspection ALEXANDER HANDY
Final 2/10/2026 Corrections Issued ALEXANDER HANDY
Green Building Final 2/10/2026 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 2/10/2026 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Final 2/10/2026 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Not Ready ALEXANDER HANDY
Smoke Detectors 2/10/2026 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Final 3/5/2026 Approved ALEXANDER HANDY
Final 3/5/2026 OK to Issue CofO ALEXANDER HANDY
Green Building Final 3/5/2026 Approved ALEXANDER HANDY
HVAC-Final 3/5/2026 Approved ALEXANDER HANDY
PLUMBING-Final 3/5/2026 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 3/5/2026 Approved ALEXANDER HANDY
Special/Order Compliance 4/15/2026 Corrections Issued ALEXANDER HANDY