4245 N VALLEY MEADOW ROAD 91436

Certificate Information: 4245 N VALLEY MEADOW ROAD 91436

Application / Permit
23016-20000-02330
Plan Check / Job No.
B23VN00998
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD, REROOF AND REPLACE DOORS AND WINDOWS PER PLANS.
Permit Issued
Issued on 3/7/2023
Issuing Office
Valley
Current Status
Permit Finaled on 4/21/2025

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/4/2023 ARTIN ZARUKIAN
Corrections Issued 2/4/2023 ARTIN ZARUKIAN
Building Plans Picked Up 2/8/2023 APPLICANT
Plan Check Approved 2/22/2023 OMAR GARNICA
Issued 3/7/2023 APPLICANT
Permit Finaled 4/18/2025 THOMAS FINNILA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/22/2023 OMAR GARNICA

Contact Information

Contractor Suchite J C Construction; Lic. No.: 1020926-B 21817 LANARK STREET #9      CANOGA PARK, CA 91304
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/26/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 7/13/2023 Approved VINCENT HANLEY
PLUMBING-Rough 7/13/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/20/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Approved VINCENT HANLEY
HVAC-Rough 10/20/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/20/2023 Approved VINCENT HANLEY
PLUMBING-Rough 10/20/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/1/2023 Approved VINCENT HANLEY
Green Building Rough 11/1/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/1/2023 Partial Approval VINCENT HANLEY
Shower Pan 11/1/2023 Approved VINCENT HANLEY
Gas Test 4/22/2024 Approved VINCENT HANLEY
Final 5/22/2024 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved THOMAS FINNILA
Smoke Detectors 5/22/2024 Approved THOMAS FINNILA
Final 5/28/2024 Corrections Issued THOMAS FINNILA
Final 7/24/2024 Corrections Issued THOMAS FINNILA
Final 4/18/2025 Permit Finaled THOMAS FINNILA