12556 W MIRANDA ST 91607

Certificate Information: 12556 W MIRANDA ST 91607

Application / Permit
23016-20000-02209
Plan Check / Job No.
B23VN00945
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-0" x 20'-0" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER WFPP.
Permit Issued
Issued on 2/22/2023
Issuing Office
Current Status
CofO Issued on 1/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2023 APPLICANT
Assigned to Plan Check Engineer 2/3/2023 MIROOSH KHACHATOORIAN
Corrections Issued 2/4/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/11/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/16/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 2/22/2023 MIROOSH KHACHATOORIAN
Issued 2/22/2023 APPLICANT
CofO in Progress 1/9/2024 JUAN VALENZUELA
Permit Finaled 1/16/2024 RUBEN SALAS
CofO Issued 1/16/2024 RUBEN SALAS
Permit Finaled 1/16/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/8/2023 CHRIS CHAHBAZ
Sewer availability Cleared 2/8/2023 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 2/9/2023 CHRIS CHAHBAZ

Contact Information

Contractor Heskel Developments; Lic. No.: 1081833-B       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 5/3/2023 Approved KIRK SANDERS
PLUMBING-Rough 5/12/2023 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 6/20/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 6/20/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 6/20/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 6/28/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Approved KIRK SANDERS
HVAC-Rough 6/28/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 6/28/2023 Partial Approval KIRK SANDERS
PLUMBING-Rough 6/28/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/6/2023 Approved KIRK SANDERS
Green Building Rough 7/6/2023 Approved KIRK SANDERS
HVAC-Rough 7/6/2023 Approved KIRK SANDERS
Insulation 7/6/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 7/6/2023 Approved KIRK SANDERS
Shower Pan 7/6/2023 Approved KIRK SANDERS
Drywall Nailing 7/12/2023 Approved KIRK SANDERS
HVAC-Rough 7/12/2023 Approved KIRK SANDERS
HVAC-Final 10/3/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 10/16/2023 Corrections Issued KIRK SANDERS
HVAC-Final 10/16/2023 Approved KIRK SANDERS
PLUMBING-Final 10/16/2023 Approved KIRK SANDERS
ELECTRICAL-Final 10/19/2023 Approved KIRK SANDERS
Final 10/19/2023 Conditional Approval KIRK SANDERS
Green Building Final 10/19/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 10/19/2023 Approved KIRK SANDERS
Final 12/21/2023 Partial Inspection JUAN VALENZUELA