1111 S FIGUEROA ST 90015
Certificate Information: 1111 S FIGUEROA ST 90015
- Application / Permit
- 23016-20000-02158
- Plan Check / Job No.
- B23VN00911
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Sports Arena (unlimited seating capacity)
- Work Description
- **eplan: ** CRYPTO.COM ARENA REFRESH 2023, INTERIOR REMOVATION FOR DEVELOPMENT OF FOUR (4) TERRACE SUITES AT THE MAIN CONCOURSE LEVEL. SCOPE INCLUDES MODIFICATION OF EXISTING SEATING TIER AND NEW INTERIOR FINISHES AND FF&E FOR THESE SPACES.
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Current Status
- Issued on 5/25/2023
Permit Application Status History
| Submitted | 2/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | JOHNNY WU |
| Corrections Issued | 3/14/2023 | JOHNNY WU |
| Quality Review Completed | 3/17/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/24/2023 | JOHNNY WU |
| Applicant returned to address corrections | 5/9/2023 | JOHNNY WU |
| Plan Check Approved | 5/9/2023 | JOHNNY WU |
| Issued | 5/25/2023 | APPLICANT |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 3/15/2023 | MENOA AGHAJANI |
| Green Code | Cleared | 3/17/2023 | JOHNNY WU |
| City owned building/parcel | Cleared | 3/30/2023 | JOHNNY WU |
| Specific Plan | Cleared | 3/30/2023 | NURI CHO |
| ZA Case | Cleared | 4/2/2023 | RYAN LY |
| DAS Clearance | Cleared | 4/4/2023 | JOHNNY WU |
Contact Information
| Architect | Szupinski,, Jan Tadeusz; Lic. No.: NA13021 | , |
| Contractor | Pcl Construction Services Inc; Lic. No.: 474555-B | , |
| Engineer | Towers,, Kevin; Lic. No.: S6625 | 6121 IROQUOIS RD WESTMINSTER, CA 92683 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 6/22/2023 | Approved | ALAN MORELOS |
| Deputy Reinf. Concrete | 6/22/2023 | Approved | ALAN MORELOS |
| Green Building Rough | 6/22/2023 | Not Ready for Inspection | ALAN MORELOS |
| METHANE-Rough | 6/22/2023 | Not Ready for Inspection | ALAN MORELOS |
| Reinforced Concrete Frame | 6/22/2023 | Not Ready for Inspection | ALAN MORELOS |
| Deputy Drilled-In Anchors | 6/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 7/7/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 7/7/2023 | Corrections Issued | KATY RAMIREZ |
| Drywall Nailing | 7/11/2023 | Approved | DARRYL ARNOLD |
| Green Building Rough | 7/13/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| METHANE-Rough | 7/13/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Reinforced Concrete Frame | 7/13/2023 | Partial Approval | JEROME BLACKWOOD |
| Green Building Rough | 7/15/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Green Building Rough | 7/15/2023 | Off-Hour Fees Due | |
| METHANE-Rough | 7/15/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| METHANE-Rough | 7/15/2023 | Off-Hour Fees Due | |
| Reinforced Concrete Frame | 7/15/2023 | Off-Hour Fees Due | |
| Reinforced Concrete Frame | 7/15/2023 | Partial Approval | JULIAN CAPUCETTI |
| Reinforced Masonry Frame | 7/18/2023 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 7/22/2023 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 7/22/2023 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 7/25/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 7/27/2023 | Conditional Approval | DARRYL ARNOLD |
| Light Gage Steel Frame | 7/27/2023 | Conditional Approval | DARRYL ARNOLD |
| Light Gage Steel Frame | 8/12/2023 | Partial Approval | TED RIES |
| Light Gage Steel Frame | 8/30/2023 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 9/19/2023 | Partial Inspection | RAFAEL CORTES |
| Final | 9/28/2023 | Partial Inspection | KATY RAMIREZ |
| Green Building Final | 9/28/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Rough | 9/28/2023 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 9/28/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Special/Order Compliance | 9/29/2023 | Partial Inspection | KATY RAMIREZ |
| Special/Order Compliance | 10/2/2023 | Partial Inspection | KATY RAMIREZ |
| Final | 11/8/2023 | Partial Inspection | KATY RAMIREZ |
| Green Building Final | 11/8/2023 | Approved | KATY RAMIREZ |
| METHANE-Final | 11/8/2023 | Approved | KATY RAMIREZ |
| METHANE-Rough | 11/8/2023 | Approved | KATY RAMIREZ |
| Reinforced Concrete Frame | 11/8/2023 | Partial Inspection | KATY RAMIREZ |
| Smoke Detectors | 11/8/2023 | Approved | KATY RAMIREZ |
| Final | 12/13/2023 | Corrections Issued | KATY RAMIREZ |
| Reinforced Concrete Frame | 12/13/2023 | Approved | KATY RAMIREZ |