12754 N GLENOAKS BLVD 91342
Certificate Information: 12754 N GLENOAKS BLVD 91342
- Application / Permit
- 23016-20000-02031
- Plan Check / Job No.
- B23VN00860
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A (N) DETACHED 20'-0" x 18'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/1/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2023 | RAMA DABADGE |
| Corrections Issued | 2/1/2023 | RAMA DABADGE |
| Building Plans Picked Up | 2/3/2023 | APPLICANT |
| Applicant returned to address corrections | 2/28/2023 | WEIJIAN HUANG |
| Issued | 3/1/2023 | APPLICANT |
| CofO in Progress | 10/2/2023 | KEVIN BERBERYAN |
| CofO Issued | 1/9/2024 | RUBEN SALAS |
| Permit Finaled | 1/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2023 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 2/3/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 2/3/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 2/23/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/11/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/11/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/11/2023 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 4/11/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/17/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 4/17/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/24/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/24/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/27/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/27/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/27/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/27/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 4/27/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 5/3/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/5/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 5/9/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/9/2023 | Partial Approval | ARAM AVEDISIAN |
| Pre-Inspection | 6/9/2023 | Approved | DAVID ANDERSON |
| Final | 7/13/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/13/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/13/2023 | Approved | MICHEL ABAJAN |
| Final | 9/27/2023 | Corrections Issued | KEVIN BERBERYAN |
| Final | 9/29/2023 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 11/2/2023 | Approved | KEVIN BERBERYAN |