14906-14908 W WOLFSKILL ST 91345
Certificate Information: 14906-14908 W WOLFSKILL ST 91345
- Application / Permit
- 23016-20000-01922
- Plan Check / Job No.
- B23VN00804
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED GARAGE TO A NEW 17'-9" x 19'-3" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP AND ENGINEERING DETAIL.
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2023 | JESSE ARELLANO |
| Corrections Issued | 1/26/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 2/10/2023 | APPLICANT |
| Plan Check Approved | 2/27/2023 | SARKIS HARABEDIAN |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 5/3/2024 | RUBEN SALAS |
| CofO Issued | 5/3/2024 | RUBEN SALAS |
| Permit Finaled | 5/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/17/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/17/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/12/2023 | Conditional Approval | MICHAEL SMITH |
| PLUMBING-Rough | 5/5/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/23/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 9/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 9/25/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/16/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/16/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 10/16/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/1/2023 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 11/30/2023 | Approved | JENNIFER RABUCHIN |
| Final | 2/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 2/2/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 2/2/2024 | Approved | JENNIFER RABUCHIN |
| Final | 2/9/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 2/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/1/2024 | Approved | JENNIFER RABUCHIN |
| Final | 5/1/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/1/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/1/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/1/2024 | Approved | JENNIFER RABUCHIN |