14906-14908 W WOLFSKILL ST 91345

Certificate Information: 14906-14908 W WOLFSKILL ST 91345

Application / Permit
23016-20000-01922
Plan Check / Job No.
B23VN00804
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) ATTACHED GARAGE TO A NEW 17'-9" x 19'-3" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP AND ENGINEERING DETAIL.
Permit Issued
Issued on 2/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2023 APPLICANT
Assigned to Plan Check Engineer 1/25/2023 JESSE ARELLANO
Corrections Issued 1/26/2023 JESSE ARELLANO
Building Plans Picked Up 2/10/2023 APPLICANT
Plan Check Approved 2/27/2023 SARKIS HARABEDIAN
Issued 2/27/2023 APPLICANT
CofO in Progress 5/1/2024 JENNIFER RABUCHIN
Permit Finaled 5/3/2024 RUBEN SALAS
CofO Issued 5/3/2024 RUBEN SALAS
Permit Finaled 5/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/17/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 2/17/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/21/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2023 Conditional Approval MICHAEL SMITH
PLUMBING-Rough 5/5/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/23/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/23/2023 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 9/8/2023 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 9/25/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/16/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/16/2023 Approved JENNIFER RABUCHIN
Green Building Rough 10/16/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 10/16/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 11/1/2023 Approved JENNIFER RABUCHIN
Pre-Inspection 11/30/2023 Approved JENNIFER RABUCHIN
Final 2/2/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/2/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 2/2/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 2/2/2024 Approved JENNIFER RABUCHIN
Final 2/9/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 2/9/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/1/2024 Approved JENNIFER RABUCHIN
Final 5/1/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/1/2024 Approved JENNIFER RABUCHIN
HVAC-Final 5/1/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/1/2024 Approved JENNIFER RABUCHIN