6935-6935 1/2 N RANCHITO AVE 91405

Certificate Information: 6935-6935 1/2 N RANCHITO AVE 91405

Application / Permit
23016-20000-01914
Plan Check / Job No.
B23VN00802
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED 1- CAR IRREGULARLY SHAPED 16'1" X 20'2" GARAGE (186 SF) & 12' X 9'6" PORTION (114 SF) OF (E) SINGLE FAMILY DWELLING (186 SF) INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22. THIS PERMIT TO INCLUDE REMODEL OF EX DWELLING - CONVERT POR OF LIVING RM INTO NEW KITCHEN & ADD BATHRM PER PLAN. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 4/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 SERGIO MUNIZ
Corrections Issued 1/28/2023 SERGIO MUNIZ
Building Plans Picked Up 2/1/2023 APPLICANT
Applicant returned to address corrections 2/24/2023 HAYATO TSUCHIYA
Applicant returned to address corrections 3/3/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 3/9/2023 MADISON ODELL
Issued 4/13/2023 APPLICANT
CofO in Progress 10/20/2023 RYAN SALAZAR
Permit Finaled 12/15/2023 RUBEN SALAS
CofO Issued 12/15/2023 RUBEN SALAS
Permit Finaled 12/15/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/2/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/2/2023 CARLOS AGUILERA
Sewer availability Cleared 2/2/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/28/2023 Conditional Approval JUAN VALENZUELA
Underground Mechanical 4/28/2023 Not Ready for Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 5/15/2023 Partial Approval RYAN SALAZAR
Underground Mechanical 5/15/2023 Approved RYAN SALAZAR
Underground Mechanical 6/12/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 7/12/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 7/12/2023 Approved RYAN SALAZAR
Green Building Rough 7/12/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 7/12/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/18/2023 Approved RYAN SALAZAR
Green Building Rough 7/18/2023 Approved RYAN SALAZAR
HVAC-Rough 7/18/2023 Approved RYAN SALAZAR
Insulation 7/26/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 7/26/2023 Approved WILLIAM WREN
Shower Pan 7/26/2023 Approved WILLIAM WREN
Drywall Nailing 7/31/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/31/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 10/11/2023 Approved RYAN SALAZAR
Final 10/11/2023 Partial Approval RYAN SALAZAR
Green Building Final 10/11/2023 Approved RYAN SALAZAR
HVAC-Final 10/11/2023 Approved RYAN SALAZAR
PLUMBING-Final 10/11/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 10/11/2023 Not Required RYAN SALAZAR
Smoke Detectors 10/11/2023 Approved RYAN SALAZAR
Final 10/20/2023 OK to Issue CofO RYAN SALAZAR