20021-20023 W LULL ST 91306

Certificate Information: 20021-20023 W LULL ST 91306

Application / Permit
23016-20000-01245
Plan Check / Job No.
B23VN00528
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO A (N) 18'-0" x 20'-4" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) PER ENGINEERING
Permit Issued
Issued on 1/27/2023
Issuing Office
Current Status
CofO Issued on 10/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2023 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 ARTIN ZARUKIAN
Corrections Issued 1/21/2023 ARTIN ZARUKIAN
Building Plans Picked Up 1/23/2023 APPLICANT
Issued 1/27/2023 APPLICANT
CofO in Progress 10/24/2023 HORACE FULTZ
Permit Finaled 10/30/2023 JOHN JANSON
CofO Issued 10/30/2023 JOHN JANSON
Permit Finaled 10/30/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/23/2023 LEE GUILBEAUX
Sewer availability Cleared 1/23/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/24/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/24/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/13/2023 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 4/21/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 4/21/2023 Partial Approval ALEXANDER HANDY
Sewer 4/21/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 5/30/2023 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 5/30/2023 Approved ALEXANDER HANDY
Green Building Rough 5/30/2023 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 5/30/2023 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 6/8/2023 Partial Approval ALEXANDER HANDY
Green Building Rough 6/8/2023 Approved ALEXANDER HANDY
Insulation 6/8/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 6/8/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 6/13/2023 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved ALEXANDER HANDY
Green Building Rough 6/13/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 6/13/2023 Partial Approval ALEXANDER HANDY
Shower Pan 6/13/2023 Approved ALEXANDER HANDY
Drywall Nailing 6/23/2023 Approved HORACE FULTZ
ELECTRICAL-Final 9/18/2023 Corrections Issued ALEXANDER HANDY
Final 9/18/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 9/18/2023 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 9/18/2023 Approved ALEXANDER HANDY
PLUMBING-Final 9/18/2023 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 9/18/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 10/17/2023 Approved HORACE FULTZ
Final 10/17/2023 Corrections Issued HORACE FULTZ
Green Building Final 10/17/2023 Approved HORACE FULTZ
HVAC-Final 10/17/2023 Approved HORACE FULTZ
PLUMBING-Final 10/17/2023 Approved HORACE FULTZ
Final 10/23/2023 OK to Issue CofO HORACE FULTZ