12759 W WELBY WAY 91606
Certificate Information: 12759 W WELBY WAY 91606
- Application / Permit
- 23016-20000-01058
- Plan Check / Job No.
- B23VN00468
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN* CONVERT EXISTING 20'x18' DETACHED GARAGE WITH 6'-6"x14" ADDITON AT 1ST FLOR AND 17'-0"x 29'-6" ADDITON AT 2ND FLOOR INTO TWO- STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - WORK PER ENGINEER.
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- CofO Issued on 4/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 1/29/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/28/2023 | ANDREW SANTIAGO |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 3/8/2024 | JOSE AVILA |
| Permit Finaled | 4/5/2024 | RUBEN SALAS |
| CofO Issued | 4/5/2024 | RUBEN SALAS |
| Permit Finaled | 4/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/2/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/6/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 6/6/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/6/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2023 | Approved | KIRK SANDERS |
| Deputy Drilled-In Anchors | 7/14/2023 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 7/20/2023 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 7/20/2023 | Partial Approval | JUAN VALENZUELA |
| Gas Test | 7/27/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/13/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 9/13/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 9/13/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 9/13/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 9/13/2023 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 9/13/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 9/15/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 9/21/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 9/29/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 10/13/2023 | Approved | JUAN VALENZUELA |
| Shower Pan | 10/23/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/30/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/8/2023 | Corrections Issued | JOSE AVILA |
| Final | 12/8/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 12/8/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/8/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 12/8/2023 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 12/8/2023 | Not Ready for Inspection | JOSE AVILA |
| Final | 2/7/2024 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 2/7/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/9/2024 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 3/1/2024 | Partial Inspection | JUAN VALENZUELA |
| Final | 3/8/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 3/8/2024 | Approved | JOSE AVILA |