5940-5942 N FULCHER AVE 91601

Certificate Information: 5940-5942 N FULCHER AVE 91601

Application / Permit
23016-20000-01037
Plan Check / Job No.
B23VN00461
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN* CONVERT 19'-5" X 25'-1" EXISTING ATTACHED GARAGE AND 7'-1" X 12'-1" PORTION OF EXISTING SINGLE FAMILY DWELLING INTO ACCESSORY DWELLIGN UNIT PER GCS 65852.2(e)(1)(A) - PER WFPP
Permit Issued
Issued on 2/1/2023
Issuing Office
Current Status
CofO Issued on 6/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2023 APPLICANT
Assigned to Plan Check Engineer 1/20/2023 DANIEL ABRAMYAN
Corrections Issued 1/22/2023 DANIEL ABRAMYAN
Plan Check Approved 1/30/2023 DANIEL ABRAMYAN
Issued 2/1/2023 APPLICANT
CofO in Progress 6/12/2024 JOSE AVILA
CofO Issued 6/25/2024 RUBEN SALAS
Permit Finaled 6/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/24/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/24/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/25/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/27/2023 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 5/1/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/5/2023 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 5/5/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/12/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/12/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/12/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/2/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 6/2/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/2/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/10/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 7/10/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 7/10/2023 Partial Approval JOHN HAYES
Special/Order Compliance 7/10/2023 Corrections Issued JOHN HAYES
Insulation 7/14/2023 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 7/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 7/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 7/18/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
Shower Pan 8/4/2023 Not Ready for Inspection JOHN HAYES
Insulation 8/14/2023 Not Ready for Inspection JOHN HAYES
Shower Pan 8/14/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 8/18/2023 Approved JOHN HAYES
Green Building Rough 8/18/2023 Approved JOHN HAYES
Insulation 8/18/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 8/18/2023 Approved JOHN HAYES
Drywall Nailing 8/30/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/30/2023 Approved JENNIFER RABUCHIN
Grounding or Bonding 11/20/2023 Partial Inspection MICHEL ABAJAN
Pre-Inspection 11/20/2023 Partial Approval MICHEL ABAJAN
Final 1/11/2024 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/11/2024 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/11/2024 Approved JOHN HAYES
Final 4/30/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/30/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/30/2024 SGSOV Not Ready JENNIFER RABUCHIN
Final 5/14/2024 Corrections Issued JOSE AVILA
Final 5/28/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved JOSE AVILA
Final 6/12/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 6/12/2024 Approved JOSE AVILA