16250 W STAGG ST 91406

Certificate Information: 16250 W STAGG ST 91406

Application / Permit
23016-20000-00977
Plan Check / Job No.
B23VN00438
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
T.I. to demo (E) non-bearing partitions at level 1, demo (E) mezzanine, (N) single story office area within the existing warehouse with new accessible restrooms; Add 2 new Accessible stalls; (N) storefront windows, relocate (E) roof hatch; add new HVAC and curb on the roof; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 6/14/2023
Issuing Office
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 SEAN SHAHMIRI
Corrections Issued 2/21/2023 SEAN SHAHMIRI
Quality Review Completed 2/24/2023 OMID HEDAYAT
Applicant returned to address corrections 3/30/2023 SEAN SHAHMIRI
Plan Check Approved 6/14/2023 SEAN SHAHMIRI
Issued 6/14/2023 APPLICANT
CofO in Progress 11/17/2023 DEANDRE HOFFMAN
Permit Finaled 11/17/2023 JEFFREY DURAN
CofO Issued 11/17/2023 JEFFREY DURAN
Permit Finaled 11/17/2023 JEFFREY DURAN

Permit Application Clearance Information

Green Code Cleared 6/1/2023 Hernan Arreola
DAS Clearance Cleared 6/7/2023 Hernan Arreola
Sewer availability Cleared 6/9/2023 LEE GUILBEAUX
"Q" conditions Cleared 6/12/2023 ASHLEY RODARTE
"T" removal Cleared 6/12/2023 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 6/12/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/12/2023 LEE GUILBEAUX
Public Works-Sewers Cleared 6/12/2023 LEE GUILBEAUX

Contact Information

Architect Torres,, Daniel J; Lic. No.: NA17341       ,
Contractor West Hills Construction Inc; Lic. No.: 578578-B 423 JENKS CIRCLE STE 101      CORONA, CA 92880
Engineer Rosepink,, Dustin; Lic. No.: S5885 24255 VIA MADRUGADA      MISSION VIEJO, CA 92692

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 7/25/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 8/2/2023 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 8/10/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 8/11/2023 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 8/22/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 8/25/2023 Partial Inspection JEFFREY FULTON
Pre-Inspection 8/29/2023 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 8/31/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 9/12/2023 Partial Approval DEANDRE HOFFMAN
T-Bar Ceiling 10/17/2023 Partial Approval DEANDRE HOFFMAN
Final 10/31/2023 Corrections Issued DEANDRE HOFFMAN
Green Building Final 10/31/2023 Approved DEANDRE HOFFMAN
Green Building Rough 10/31/2023 Approved DEANDRE HOFFMAN
Reinforced Masonry Frame 10/31/2023 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 10/31/2023 Approved DEANDRE HOFFMAN
Final 11/7/2023 Partial Inspection DEANDRE HOFFMAN
Final 11/17/2023 OK to Issue CofO DEANDRE HOFFMAN